Vertiv™ XTE 802G Generator Room Walk-In-Cabinet Description and Installation Manual
32
Combo Concrete / Gravity Platform Installation Procedure
1.
The On The Ground (Gravity) Foundation Kit ships assembled so lift and set it on grade or concrete in desired location.
2.
Level the platform by adjusting the leveling hardware between the frame and the nine leveling points. Start by leveling the
four corners first then adjust the remaining leveling points. Once leveling is achieved secure the hardware.
3.
Install the stairs on the XTE 802 using the provided hardware.
4.
Install the stairs on the XTE 802G using the provided hardware.