Caution:
Do not turn on the power to any components while connecting the power
cords. The components must be turned on in a specific sequence to ensure correct
communication.
To connect the power cables
1
Verify that the AC power supply input for the appliance and for the storage
shelf is within one of these ranges.
■
100 - 127 VAC at 50/60 Hz
■
200 - 240 VAC at 50/60 Hz
2
For each shelf, obtain two power cords that are appropriate for your region and
equipment.
3
Locate the power sockets in the shelf.
4
Connect one cable between each socket and a socket on the Power Distribution
Unit (PDU) for your rack.
Note:
The following steps apply if you removed the appliance from the rack to
install additional components.
5
Obtain two power cords for your appliance.