INSTALLATION INSTRUCTIONS: Viewline 52 mm
TU00-0752-8707102
Technische Änderungen vorbehalten - Technical details subject to change
TU00-0752-8707102
Ammeter
Depending on the configuration, insert the cable into
the 8-pin contact enclosure according to the following
pin assignment. The contacts must audibly lock into
place.
Pin 1 - Term. 30 - battery 12/24 V
Pin 2 - Term. 31 - ground
Pin 3 - signal ground
Pin 4 - Term. 15 - ignition plus
Pin 5 - sensor signal
Pin 6 - Term. 58 - lighting
Pin 7 - programming port Tx
Pin 8 - programming port Rx
Now insert the plug into the gauge. Note the inverse
polarity protection nose in the process.
4
8
1
5
Place the flush mount seal A2C53215640 on the
instrument glass.
Put the instrument into the drill hole from the back.
Adjust the instrument so that the gauge is level and
fasten it to the stud bolts on the rear side of the panel,
using the flush mount fixing bracket A2C59510864.
If the instrument is mounted flush (i.e., from the back
so that the instrument glass and the panel form one
plane), the front ring must be removed. Press the
instrument glass with both thumbs, while at the same
time pressing the front ring forward from the instrument
with both index fingers. Note the use of a tool in the
adjacent figure.
2
1
Flush assembly
The recommended panel thickness is 1.5 to 3 mm.
The drill hole must have a diameter of 48.1 mm.
Ensure that the installation location is level and has no
sharp edges.
1.5...3 mm
dia. 48.1 mm
• Do not drill holes or ports in load-bearing or stabilizing stays or tie bars!
• Note the necessary clearance behind the drill hole or port at the installation location. Required mounting depth:
65 mm.
• Drill small ports; enlarge and complete them, if necessary, using taper milling tools, saber saws, keyhole saws
or files. Debur edges. Follow the safety instructions of the tool manufacturer.