11
4 Place the duct pipes in the Unibody
NOTICE
Use the provided EPP glue for the lower duct pipe. The lower duct pipe is the condensate
drain and
needs to be water tight
. Apply PVC glue to the last 3 cm of the duct and to
the white ring. Make an airtight connection: the air in the ducts can be very cold. No
warm, moist indoor air may reach the cold ducts.
1.
Put PVC glue on the white ring which is located in the inside of the stale air output
socket (see fig. 9). Do not put PVC glue on the freh air input tube.
fig. 9
Put PVC glue in the stale air output socket on the white ring only
2. Place the duct pipes into the Unibody.
Make sure the lips are pointed towards the bottom side of the Unibody.
These are needed to mate with the outside wall grills.
fig. 10 Place the PVC duct pipes into the Unibody
PVC glue
NO PVC glue
Bottom side
Summary of Contents for fresh-r everywhere On-The-Wall
Page 9: ...9 fig 6 Check the dimensions of the corner holes before drilling 243 mm 105 mm 111 mm 1055 mm...
Page 19: ...19 fig 25 Lip should overlap with the edge of the grilles...
Page 29: ...29 15 1 3 Outer wall template Dimensions are in mm Dimensions in brackets are in inches...
Page 33: ...33...
Page 34: ...34...
Page 35: ...35...
Page 36: ...www vaventis com 2015 by Vaventis B V All right reserved...