The initialisation process can be tracked at the LED ring of the
On/Off button.
LED ring
colour
LED action
Operating state
Green
Flashes every second
Duration approx. 90 s
System check
Green
Steady light
Ready
Red
Steady light
Probable error:
The battery modules have
not yet been configured.
Continue with commissioning!
LED ring
colour
Possible cause
Remedy
White
On/Off button
not pressed
Press On/Off button
Fuse not switched on
Switch on fuse
No
AC grid connection
Check AC grid connection
and establish, if necessary
Switch defective
Check switch and replace, if
necessary