Before installing and connecting the condensate inlet pipes upstream of the receiver and outlet pipes downstream 
of the pumps, make sure that all foreign matter or installation debris are flushed out. 

 

Strainers should  be  installed upstream of the condensate receiver in case there is a potential for debris to carry 
over into it. The strainer screens should be cleaned regularly.  

 

The installer must check, to ensure, that there  are no foreign bodies inside the  pipes, and  that  the  piping  where 
the equipment will be connected also does not contain any foreign bodies. 

 

It  is  recommended  the  isolation  of  the  equipment  and  accessories  to  prevent  accidents  by  burns.  In  specific 
applications, integral devices should be fitted to limit the highest surface temperature. 

5.4 Compressed air supply 

 

 

If a pneumatic control valve and other pneumatic equipment is installed a suitable air supply will be required. 3  - 6 
bar may be required, depending upon the actuator selected or equipment (revert to the specific datasheet/IMI of 
equipment  included).  Air  filter  regulators  must  be  used  to  ensure  the  correct  pressure  is  supplied  to  each 
valve/equipment. 

 

5.5 Electric supply and specifications 

 

 

 

 

It  should  be  granted  equipotentiality  of  the  metal  parts  (of  devices  and  tubes)  and  earthing.  The  structure  is 
supplied with an earthing connection point that if not connected, should be connected during installation. If thermal 
isolation is present the electrical resistance value between parts should be verified. 

Electrical  connection  of  the  equipment  should  only  be  carried  out  by  qualified  and  experienced  personnel,  and 
must comply with the current regional electric regulations and standards.  

 

 
 

 

Before  connecting  the  power  supply  to  the  ECRU  control  panel,  check  voltage,  frequency  and  electric  cable 
section  to  make  sure  that  the  electrical  supply  meets  the  specifications  stated  on  the  control  panel  and  wiring 
diagram, supplied inside the control panel. 

 

Connect power supply into the control panel through a suitable protection isolation switch and in accordance with 
the wiring diagram supplied with the unit. Mains supply is 

connected to the DIN rail terminals. Protective earth ‘PE’ 

must be appropriately connected to the respective terminal.  

 

After commissioning into service make sure the control panel enclosure is properly closed.  

 

It is recommended that an electrical safety check is performed before commencing the start-up procedure. Carry 
out tests on any alarms or protective devices.  

 
 

 

 

Fig. 5 

– Customer connections 

Summary of Contents for ADCAMAT ECRU

Page 1: ...VALSTEAM ADCA We reserve the right to change the design and material of this product without notice IMI ECRU E 01 18 INSTALLATION AND MAINTENANCE INSTRUCTIONS ELECTRIC CONDENSATE RECOVERY UNIT ECRU...

Page 2: ...9 5 ASSEMBLY INSTALLATION AND CONNECTION 10 5 1 Assembly 10 5 2 Installation area requirements 10 5 3 Pipping connection 10 5 4 Compressed air supply 11 5 5 Electric supply and specifications 11 6 STA...

Page 3: ...to Work system is implemented it must be complied with Do not remove the nameplate attached to the equipment Serial number and other useful information are stamped on it Under normal operation conditi...

Page 4: ...s electric condensate recovery units are recommended in the transfer of high temperature water such as hot condensate to a higher elevation or pressure This condensate is usually used as boiler feed w...

Page 5: ...AISI 316 1 4401 P235GH 1 0325 3 Ball valve ADCA M3I MWS1 4 Strainer ADCA IS16F 5 Electric pump 6 Check valves ADCA RD40 7 Pressure gauge ADCA MAN100 8 Siphon ADCA GSU 9 Gauge cock ADCA GC400 10 Globe...

Page 6: ...er for the specific IMI CONNECTIONS SIZE Model d1 d2 d3 d4 EC255 DN50 DN50 DN80 DN50 EC600 DN65 DN65 DN100 DN65 EC850 DN100 DN100 DN100 DN100 DIMENSIONS mm Model A B C D E F G H I J L M N O P EC255 14...

Page 7: ...225 l vessel 4T10 10 m3 h at 10 metres with 600l vessel 10T10 10 m3 h at 20 metres with 600l vessel 10T20 20 m3 h at 10 metres with 600l vessel 20T10 20 m3 h at 20 metres with 600l vessel 20T20 30 m3...

Page 8: ...will continue rising and in that case as soon as it reaches the Pump cascade level both pumps will run simultaneously to relieve this peak demand The pumps will stop running as soon as the water leve...

Page 9: ...t protects against corrosion during transportation and storage Equipment s should be protected from impacts and forces during transportation and storage The eyebolt placed on top of the receiver are e...

Page 10: ...es in the supports Ensure that the ground is levelled and that the adequate fixing elements are use according to the type of concrete The installer should analyze the transfer of vibration to the syst...

Page 11: ...ct pressure is supplied to each valve equipment 5 5 Electric supply and specifications It should be granted equipotentiality of the metal parts of devices and tubes and earthing The structure is suppl...

Page 12: ...with radial polarity besides the magnetic switches from the top down The contact of the switches should be all open at this point In case of any doubt use a multimeter set to continuity and check each...

Page 13: ...own all water accumulated inside the receiver to a safe drain point by opening the drain outlet on the bottom of the receiver Drain down all water inside the pump s casings through the drain port poss...

Page 14: ...vel and high water level alarms To perform this test start by setting the pump operating mode to the Off position Allow water to fill up the vessel until it is discharging from the overflow The High w...

Page 15: ...apacity 1 Suction valve partially closed 2 Delivery valve partially closed 3 Incorrect direction of rotation 1 Open valve fully 2 Adjust valve by the required amount to prevent cavitation 3 Check elec...

Page 16: ...or mechanical damage that may represent a health safety or environmental risk must be provided in writing by the distributors and costumers when returning products to Valsteam ADCA engineering Health...

Page 17: ...ure C Normas Harmonizadas utilizadas Harmonized Standards EN61439 1 IEC 60204 1 EN 61000 6 1 EN 61000 6 2 EN 61000 6 4 EN ISO12100 2010 Especifica es T cnicas utilizadas Used Technical specifications...

Reviews: