BOILER INSTALLATION SEQUENCE
Fig. I.4: Fitting the boiler
Fitting the boiler
●
Lift the boiler (
3
) up to the wall so
that it is slightly above the hanging
bracket (
1
).
●
Lower the boiler slowly onto the
hanging bracket so that the cross
member at the rear of the boiler
fully engages onto the hanging
bracket.
Note:
Lift the boiler from either side
at the bottom edge.
Install the flue system
Install the flue system (refer to
separate air/flue duct installation
instructions).
Fitting the boiler hanging
bracket
Fix the hanging bracket (
2
) to the wall
using the screws supplied. (it may be
necessary to use additional or
alternative fixings to ensure adequate
support).
Note:
If the boiler is to be fitted in a
timber framed building ensure that
the bracket is secured to a
substantial part of the timber frame
capable of taking the weight of the
boiler.
Summary of Contents for TURBOmax Pro 2 E
Page 31: ...31 COMMISSIONING PART I...
Page 32: ...32 COMMISSIONING PART I 2 5 3 4 Fig Com 1 Draining the heating system Eor B S 207 0GB_Pro...
Page 65: ...65 FAULT FINDING...
Page 71: ...71...