A. Verify Proper Sequence Of
Operation
The sequence can be followed via the
diagnostic indicator lamps on the Hon-
eywell S9301A integrated boiler control
in
Figure #16.
This is the normal
sequence of operation. A more detailed
sequence of operation containing po-
tential faults can be found in the service
hints section.
seQUeNce oF oPeratioN
“DiaGNostic
iNDicator
laMPs”
“Power ON, boiler standing by. Lamp A is illuminated
indicating 2 Volt power is being supplied to the inte-
grated control.”
A.
B.
C.
D.
E.
Thermostat calls for heat, energizing system circulator
A.
B.
C.
D.
E.
“Integrated boiler control goes through self check of
internal circuitry (1-2 seconds) and energizes draft
inducer”
A.
B.
C.
D.
E.
“Draft inducer comes up to speed and establishes com-
bustion airflow, causing the normally open differential
pressure air proving switch contacts to close. Lamp B is
illuminated indicating that combustion airflow is proved
and the 15 second pre purge cycle”
A.
B.
C.
D.
E.
CHECK OUT PROCEDURE AND ADJUSTMENT
Figure 16 - Indicator Lamps
Summary of Contents for UB90-100
Page 15: ...15 Near Boiler Piping Figure 2 Single Zone Boiler Piping ...
Page 16: ...16 Figure 3 Multi zone Boiler Piping With Zone Valves Near Boiler Piping ...
Page 19: ...19 Figure 6 Diaphragm Type Expansion Tank Piping Near Boiler Piping ...
Page 20: ...20 Figure 7 Conventional closed type Expansion Tank Piping Near Boiler Piping ...
Page 27: ...27 Combustion Air and Vent Pipe Figure 11 Combustion Air and Vent Piping ...
Page 32: ...32 Electrical Wiring Figure 13 Field Wiring Connections ...
Page 53: ...53 DETAILED SEQUENCE OF OPERATION ...
Page 57: ...57 TROUBLESHOOTING CHART 2 TROUBLESHOOTING ...
Page 58: ...58 TROUBLESHOOTING CHART 3 TROUBLESHOOTING ...