![USC LPV Series Operator'S Manual Download Page 19](http://html.mh-extra.com/html/usc/lpv-series/lpv-series_operators-manual_1064064019.webp)
Page 19
LPV SEED TREATER
LPV AUTOMATED TREATER SET
-
UP (ALL LPV TREATERS)
The LPV Treater
CAN NOT
be lifted using the forklift
pockets and or transported without all four of the shipping
brackets re
-
installed. Failure to do so may cause damage
to the tilting frame.
Le LPV Traiteur NE PEUT PAS être soulevée à l'aide des
passages de fourches et ou transporté sans les quatre
supports de transport ré
-
installé. Ne pas le faire peut
causer des dommages au châssis basculant.
! AVERTISSEMENT
5.
Install the drum lift actuator kit (03
-
17
-
0111) that is shipped separately using the 6
steps below. (A through F)
STEP C:
Lower the drum slowly until the drum
frame is resting on the dead stop pins on both
sides of the treater frame.
STEP A:
Support the discharge end of the treater
drum using the lift ring at the top of the discharge
assembly.
STEP B:
Remove all four of the shipping support
brackets. Save for reuse if treater is moved.