3.1.3 Place of installation protection
Public access to installation site is restricted. It must be clearly demarcated with appropriate means during the
installation works and testing duration. Remove protections only after the success of the commissioning tests.
3.2. Receipt of the material
Each bollard is supplied on a pallet (Pallets are treated in compliance with ISPM15).
The technical control unit is supplied on another pallet (also treated in compliance with ISPM15) with separate options
and accessories.
The material is packaged with straps, wrapped in heat-shrinkable film and identified.
Upon delivery, the material must be checked (items, quantities, conditions) and stocked on the original pallets, in a clean
and dry room until its installation.
3.3. Unpacking and handling the bollard
3.3.1. Unpacking the bollard
Unpacking precautions:
Before cutting the straps that bind the bollard on the pallet, check that the bollard stands stable on the pallet and that
the pallet is in good condition, considering the bollard's significant weight.
Each bollard is wrapped, at the top and bottom with yellow adhesive tape mentioning "Do not remove plastic film"., in
five different languages.
THE PACKAGING PLASTIC FILM MUST BE LEFT AROUND THE CASING so that, later, when the polyurethane
foam is injected between casing and excavation inner wall, the bollard stands protected from the polyurethane foam.
Cut the plastic as shoon below and remove both plastic extremities.
To unpack, use a cutter to cut the
plastic film at the top, just above
the yellow adhesive tape.
In the same way, cut the plastic
film at the bottom, just under the
yellow adhesive tape.
Figure 14: Bollard wrapped in heat-shrinkable
film upon receiving