5.
Commissioning
When all electrical and gas connections have been completed and tested in
accordance with all instructions, codes and regulations then the instrument is ready
to be powered up.
The following work must be carried out when commissioning the unit:
Remove the transport tie wraps and transport screws from the specific gravity cell.
The body of the cell must hang free on the springs and may not come into contact
with the sides of the bracket. The screw should be removed and stored and the
following diagram illustrates the process.
Figure 15: Specific Gravity cell shown locked for transport
Figure 16: Specific Gravity cell shown in its operating position