PART II: INSTALLATION
25
Follow the electrical diagrams attached to the manual for the connections to the terminal strip.
The electrical panel is supplied complete with a terminal strip for the connection to the system electrical line and, in case of on board
control panel, a plug for the connection to the modulation probe (if any).
Rotation of electric motor
Once the electrical connection of the burner is executed, remember to check the rotation
of the electrical motor (pump motor if any, and fan motor) . The motor should rotate accor-
ding to the “arrow” symbol on the body. In the event of wrong rotation, reverse the three-
phase supply and check again the rotation of the motor.
NOTE: the burners are supplied for three-phase 380/400/415/480 V supply, and in the case of three-phase 220/230/240 V sup-
ply it is necessary to modify the electrical connections into the terminal box of the electric motor and replace the overload
tripped relay.
Note on electrical supply
In the case where the power supply of the AUXILIARIES of the phase-phase burner (without a neutral), for the flame detection it is
necessary to connect the RC circuit Siemens between the terminal 2 (terminal X3-04-4 in case of LMV2x, LMV3x, LMV5x, LME7x) of
the base and the earth terminal, RC466890660. For LMV5 control box, please refer to the clabeling recommendations avaible on the
WARNING: (only for double stage and progressive burners) The burner is provided with an electrical bridge
between terminals 6 and 7; when connecting the high/low flame thermostat, remove this bridge before connecting
the thermostat.
Any cable connection or hook-up to the grid must be carried out by qualified, informed and trained personnel,
directly coordinated and authorized by Technical Service. Always check in advance that the system electrical
interlock is fitted with a safety circuit breaker.
WARNING! It is forbidden to use the fuel pipes for the execution and/or completion of the grounding
The system must comply with the current regulations.
Earth the system; always check in advance the connection, functionality and compliance with the health and safety principles of the earth
cable. If in doubt, ask for an accurate inspection by qualified technical engineers.
Check the connection to the grounding system.
Do not use any extraneous conductive parts (i.e. fuel feeding pipes, metal structures ...) to connect the burner to ground.
In connecting the supply wires to the burner MA terminal strip, ensure that the earth wire is longer than the phase and neutral wires.
Careful not to invert the phase and neutral connections
Fit the burner power line with an omnipolar disconnector and differential switch, a thermo-magnetic circuit breaker or fuses.
Supply the burner with a flame retardant cable with a section suitable to the installed power (see electrical diagram enclosed), paying
attention to the voltage values printed on the burner plate.
Always check in advance the protection from overcurrents and electromagnetic interference of the power supply. If these and other values
do not match the threshold data stated by the manufacturer, isolate the burner from all power sources and contact the Authorized Techni-
cal Service urgently.
Check that the voltage of the system and burner motors match the voltage of the power grid (+/- 10%).
Ensure the IP protection rating is consistent with the installation place and environment characteristics
Before carrying out any operation on the machine electrical panel, open the system omnipolar disconnector and move the switch on the
burner panel to OFF.
In any case:
use suitably protected and safe burner/boiler supply and tracking cables;
avoid using extensions, adaptors or multiple sockets.
For further information, refer to the electrical diagram.
ATTENTION: check the calibration of the thermal relay sensor (+5% ÷
+10% rated value).
DANGER! Incorrect motor rotation can seriously damage property and injure people.
Summary of Contents for G258A
Page 46: ......
Page 47: ......
Page 49: ...Service manual AZL2x LMV2x 3x Burner Management System M12916CD Rev 3 3 01 2017...
Page 56: ...8 Parameters level heating engineer...
Page 98: ...50 ERROR CODE TABLE...
Page 99: ...51...
Page 100: ...52...
Page 101: ...53...
Page 102: ...54...
Page 103: ...55...
Page 104: ...56...
Page 105: ...57...
Page 106: ...58...
Page 107: ...59...
Page 108: ...60...
Page 109: ...61...
Page 110: ...62...
Page 111: ...63...
Page 112: ...64...
Page 117: ......
Page 118: ......
Page 119: ......
Page 134: ......
Page 143: ......
Page 144: ......
Page 145: ...MANUAL FOR OPERATION AND CALIBRATION MODULATOR SIEMENS RWF 40 M12905CH Rev 07 11 09...
Page 161: ...RWF50 2x RWF50 3x User manual M12922CB Rel 1 0 07 2012...
Page 176: ...16 Note Specifications and data subject to change Errors and omissions excepted...
Page 177: ...KM3 Modulator USER MANUAL M12927CA Rel 1 0 10 2020...
Page 178: ...M12927CA MOUNTING 2...
Page 194: ...1 RWF55 5X RWF55 6X User manual M12926CA Rel 0 1 10 2015...
Page 195: ...2 DEVICE INSTALLATION Fixing system Drilling dimensions...
Page 216: ......
Page 217: ...23 Note Specifications and data subject to change Errors and omissions excepted...