Combine the 1400 mm pipes placing the 10 cm small tubes exactly at half junction (fig.4-5).
Slide the sleeves on joints and heat up to the correct temperature (Figure 6)
Drill a small 2-3 mm hole on the same axis in the center in both junctions (fig.7)
NOTE
: It’s important to check that the holes are facing down before heating conduits that hold whole
side element to the curves
Fig.4
Fig.5
Fig.6
Fig.7
FIXING / ADJUSTMENT OF “T” SUPPORT
adjust in the direction
of the arrows so that
the central element is
parallel to the external
elements
Adjust in the direction of
the arrows to align the
side element before fixing
the joint
…………………………………………………………………………...
Insert the T shaped tube to the end of the antenna central element.
The tube has sufficient length to let the element slide inside, this allows a
telescopic adjustment in the direction of the arrows which is useful to set the correct position of the T,
so that the whole side panel stays perfectly in line (only aesthetic factor). Any alignment which is not
perfect will not compromise in any way antenna operation.
Once the exact spot is found, apply the heat shrink sleeve to lock the T-tube to the end of the telescopic
element.
Move laterally the T inserted into the side panel in the sense of <
arrows
> to adjust
parallelism between the antenna elements. It is not necessary to lock the T element, you can also leave
it free to slide, so it will always find its natural position.