A.

  General Housekeeping (Continuous).

1.  Keep boiler area clear and free of combustible 

materials and obstructions to the free flow of 

combustion and ventilation air to the boiler.

2.  Do not store or use gasoline or other flammable 

vapors, liquids or sources of hydrocarbons in the 

vicinity of the boiler or any other appliance.

3.  Do not store or use halogen-containing products 

(bleaches, cleaners, fabric softeners, refrigerants, 

chemicals, etc.) in the vicinity of the boiler.

B.

  Inspect Inlet Air and Vent System (Monthly).

 Check 

the following. If corrective action is required contact 

qualified service agency.
1.  Inlet air terminal and vent terminal must be free of 

obstruction, undamaged, with screens securely in 

place.

2.  Inlet air terminal, vent terminal, and wall thimble (if 

used) must be weather-tight.

3.  Inlet air pipe and vent pipe must be full round 

shape, showing no damage from impact or excessive 

temperature.

4.  Inlet air pipe and vent pipe must be supported at 

minimum 5 foot intervals and must not sag.

5.  All inlet pipe joints must be secure and airtight.
6.  All vent pipe joints must be secure and watertight.
7.  Condensate drain (if used) must have minimum 6 

inch trap and allow condensate to flow freely. To 

clean:
a.  Disconnect condensate drain from drain fitting.

b.  Flush condensate drain with water.

c.  Securely fasten condensate drain to drain fitting, 

providing gas-tight and water-tight seal.

C. 

Inspect Pilot and Main Burner Flames (Monthly).

1.  Remove jacket front panel. 
2.  View flames through combustion area enclosure.  

See Figure 1.

3.  Adjust thermostat to highest setting.
4.  Check pilot flame. See Figure 4. The pilot produces 

three (3) flames. The center flame should be steady, 

medium hard blue enveloping 

3

/

8

 to ½ inch of 

sensing probe. If flame is yellow and lazy, follow 

instructions TO TURN OFF GAS TO APPLIANCE 

(see Figure 2), and contact qualified service agency.

5.  Check main burner flames. See Figure 5. Flame 

should have clearly defined inner cone with no 

yellow tipping. Orange-yellow streaks caused 

by dust should not be confused with true yellow 

tipping. If yellow flames are observed, follow 

instructions TO TURN OFF GAS TO APPLIANCE 

(see Figure 2), and contact qualified service agency.

6.  Adjust thermostat to normal setting.

D.

  Schedule Inspection by Qualified Service Agency 

(Annual or at Beginning of Heating Season).

 For 

continued safe operation a qualified service agency 

must provide a more detailed inspection of burners, heat 

exchanger and vent system, and provide maintenance 

as specified in Installation, Operating and Service 

Instructions.

WARNING

Service on this boiler should be undertaken only by trained and skilled personnel from a qualified service 

agency.  Inspections  should  be  performed  at  intervals  specified  in  Installation,  Operating  and  Service 

Instructions and this manual. Maintain manuals in a legible condition.
Keep boiler area clear and free of combustible materials, gasoline and other flammable vapors and liquids.
Do not place any obstructions in boiler room that will hinder flow of combustion and ventilation air.

Figure 4: Pilot Burner

Summary of Contents for ESC

Page 1: ...SEMENT Assurez vousdebien suivre les instructions données dans cette notice pour réduire au minimum le risque d incendie ou d explosion ou pourévitertoutdommagematériel toute blessure ou la mort Ne pas entreposer ni utiliser d essence ni d autres vapeurs ou liquides inflammables dans le voisinage de cet appareil ou de tout autre appareil QUE FAIRE SI VOUS SENTEZ UNE ODEUR DE GAZ Ne pas tenter d al...

Page 2: ...ce RCF parts or attempt any service or repair work involving RCF without wearing the following protective gear 1 A National Institute for Occupational Safety and Health NIOSH approved respirator 2 Long sleeved loose fitting clothing 3 Gloves 4 Eye Protection Take steps to assure adequate ventilation Wash all exposed body areas gently with soap and water after contact Wash work clothes separately f...

Page 3: ...ained and skilled personnel from a qualified service agency 3 Pressure Switch See Figure 1 A device which automatically prevents or interrupts boiler operation when the induced draft blower fails to move sufficient combustion air for proper burner operation Boiler operation resumes automatically when sufficient combustion air flow is reestablished 4 Electronic Ignition System The Electronic Igniti...

Page 4: ...4 Figure 1 Control Locations ...

Page 5: ...5 Figure 2 Operating Instructions NOTE YOUR BOILER IS EQUIPPED WITH A HONEYWELL VR8204 OR VR8304 GAS VALVE PLEASE FOLLOW THESE OPERATING INSTRUCTIONS ...

Page 6: ...on Source Off Main Gas On Call For Heat Ends Standby Intelligent Hydronic Control can display typical Delay 60 Seconds Ignition Source Off Pilot Gas Off Main Gas Off Blower Off Circulator Output De Energized Standby Continuous Retry Self Testing Waiting for Pressure Switch to Open Waiting for Limit to Close Waiting for Pressure Switch to Close Pilot Flame Proven Pilot Flame Not Proven ...

Page 7: ...ner Flames Monthly 1 Remove jacket front panel 2 View flames through combustion area enclosure See Figure 1 3 Adjust thermostat to highest setting 4 Check pilot flame See Figure 4 The pilot produces three 3 flames The center flame should be steady medium hard blue enveloping 3 8 to inch of sensing probe If flame is yellow and lazy follow instructions TO TURN OFF GAS TO APPLIANCE see Figure 2 and c...

Page 8: ...mpany product distributor Should you require assistance in locating a U S Boiler Company product distributor in your area or have questions regarding the availability of U S Boiler Company brand products or repair parts please contact U S Boiler Company Customer Service at 717 481 8400 or Fax 717 481 8408 ...

Reviews: