Overview  

For an optimal integration of NINA-B1 series modules in the final application board, it is recommended to follow 
the design guidelines stated in this chapter. Every application circuit must be properly designed to guarantee the 
correct functionality of the related interface, however a  number of points require high attention during the 
design of the application device. 
The following list provides important points sorted by rank of importance in the application design, starting from 
the highest relevance: 
1.

 

Module antenna connection: 

Ant 

pad. 

Antenna circuit affects the RF compliance of the device integrating NINA-B1  modules with applicable 
certification schemes. Follow the recommendations provided in section 3.2 for schematic and layout design. 

2.

 

Module supply: 

VCC

VCC_IO

, and 

GND

 pins.  

The supply circuit affects the performance of the device integrating NINA-B1 series  module.  Follow the 
recommendations provided in section 3.3 for schematic and layout design. 

3.

 

Analog signals: GPIO 
Analog signals are sensitive to noise and should be routed away from high frequency signals.  

4.

 

High speed interfaces: 

UART, SPI

 and 

SWD 

pins. 

High speed interfaces can be a source of radiated noise and can affect compliance with regulatory standards 
for radiated emissions. Follow the recommendations provided in sections 3.4.1 and 2.4.2 for schematic and 
layout design. 

5.

 

System functions: 

RESET_N

I2C

GPIO

 and other 

System input and output pins

.  

Accurate design is required to guarantee that the voltage level is well defined during module boot.  

6.

 

Other pins:    
Accurate design is required to guarantee proper functionality. 

3.2

 

Antenna interface 

As the unit cannot be mounted arbitrary, the placement should be chosen with consideration so that it does not 
interfere with radio communication. The NINA-B112 with an internal surface mounted antenna cannot be 
mounted in a metal enclosure. No metal casing or plastics using metal flakes should be used. Avoid metallic 
based paint or lacquer as well. The NINA-B111 offers more freedom as an external antenna can be mounted 
further away from the module.  

 

According to FCC regulations, the transmission line from the module’s antenna pin to the 

antenna or antenna connector on the host PCB is considered part of the approved antenna design. 
Therefore, module integrators must either follow exactly one of the antenna reference design used in 
the module’s FCC type approval or certify their own designs. 

3.2.1

 

RF transmission line design (NINA-B111 only) 

RF transmission lines, such as the ones from the 

ANT 

pad up to the related antenna connector or up to the 

related internal antenna pad, must be designed so that the characteristic impedance is as close as possible to  
50 

.  Figure 10  illustrates the design options and the main parameters to be taken into account when 

implementing a transmission line on a PCB:  

 

The micro strip (a track coupled to a single ground plane, separated by dielectric material)  

 

The coplanar micro strip (a track coupled to ground plane and side conductors, separated by dielectric 
material) 

 

The strip line (a track sandwiched between two parallel ground planes, separated by dielectric material). 

Summary of Contents for NINA-B111

Page 1: ...th low energy modules With embedded Bluetooth low energy stack and u blox connectivity software these modules are tailored for OEMs who wish to have the shortest time to market The OEMs can also embed...

Page 2: ...B111 NINA B111 00B 00 1 0 0 N A Mass Production NINA B111 01B 00 2 0 0 N A Mass Production NINA B111 02B 00 3 0 1 N A Initial Production NINA B112 NINA B112 00B 00 1 0 0 N A Mass Production NINA B112...

Page 3: ...4 1 Module reset 11 1 4 2 Internal temperature sensor 11 1 5 Debug Serial Wire Debug SWD 11 1 6 Serial interfaces 12 1 6 1 Universal Asynchronous Serial Interface UART 12 1 6 2 Serial Peripheral Inter...

Page 4: ...nes 35 3 6 1 General considerations for schematic design and PCB floor planning 35 3 6 2 Module placement 35 3 6 3 Layout and manufacturing 35 3 7 Module footprint and paste mask 36 3 8 Thermal guidel...

Page 5: ...B flash and 64 kB RAM it offers the best in class capacity for customer applications running on top of the Bluetooth low energy stack using SDK from Nordic Semiconductor or Arm Mbed Additionally NFC a...

Page 6: ...er Arm Mbed Nordic SDK or Wirepas development environment inside the NINA B1 module The different software options are described in more detail in section 2 1 2 Pin configuration and function 1 2 1 Pi...

Page 7: ...s pin assignment top view The grey pins in the center of the modules are GND pins The outline of NINA B111 ends at the dotted line as shown in Figure 2 where the antenna area of NINA B112 begins All d...

Page 8: ...an NFC field to the NFC pins when they are configured as GPIOs Doing so may cause permanent damage to the module When driving different logic levels on these pins in GPIO mode a small current leakage...

Page 9: ...ITCH_1 and SWITCH_2 during a reset and holding it low for 10s will make the module restore all factory settings GPIO_16 16 P0 28 I O General purpose I O Pin is analog capable UART_DTR Can be used to i...

Page 10: ...o signal groups while in Non powered mode to avoid damaging the module 1 3 Supply interfaces 1 3 1 Main supply input The NINA B1 series uses an integrated DC DC converter to transform the supply volta...

Page 11: ...ween active and idle duty cycle of the specific application Although some DC DC can achieve high efficiency at extremely light loads a typical DC DC efficiency quickly degrades as idle current drops b...

Page 12: ...nnect and or toggle connectable status Enable disable the rest of the UART interface Enter wake up from the sleep mode See the NINA B1 series Data Sheet 2 for characteristic information about the UART...

Page 13: ...t Event trigger Interrupt event trigger to the software application Wake up event Any ADC input 8 10 12 bit analog to digital converter Any analog Analog comparator input Compare two voltages capable...

Page 14: ...gh a 50 transmission line to allow reception of radio frequency RF signals in the 2 4 GHz frequency band Choose an antenna with optimal radiating characteristics for the best electrical performance an...

Page 15: ...M installer must certify his design with respective regulatory agencies 1 8 2 Integrated antenna NINA B112 The NINA B112 is equipped with an integrated antenna on the module This will simplify the int...

Page 16: ...connectivity software The u blox connectivity software enables the use of the Bluetooth Low Energy functions controlled by AT commands over the UART interface Examples of supported features are u blo...

Page 17: ...l it automatically e Read the information in the SDK Release Notes and check the nRF5 Software Development Kit documentation available at http infocenter nordicsemi com Nordic tools More information a...

Page 18: ...fine BUTTONS_ACTIVE_STATE 0 define BUTTONS_LIST BUTTON_1 BUTTON_2 define BSP_BUTTON_0 BUTTON_1 define BSP_BUTTON_1 BUTTON_2 define RX_PIN_NUMBER 5 define TX_PIN_NUMBER 6 define CTS_PIN_NUMBER 7 define...

Page 19: ...ble getting started Mbed CLI is the name of the Arm Mbed command line tool which enables the full Mbed workflow such as repositories version control maintaining dependencies updating from remotely ho...

Page 20: ...inNames h file should declare and define a couple of enumerations to configure the custom pin mapping Figure 6 and Figure 7 show the contents of the PinNames h file in the case of EVK NINA B1 ifndef M...

Page 21: ...clude cmsis h ifdef __cplusplus extern C endif typedef enum PIN_INPUT PIN_OUTPUT PinDirection define PORT_SHIFT 3 typedef enum nRF52 pin names p0 0 p1 1 p2 2 p3 3 p4 4 p5 5 p6 6 p7 7 p8 8 p9 9 p10 10...

Page 22: ...NINA B1 board LED1 NINA_B1_GPIO_1 Red LED2 NINA_B1_GPIO_7 Green SW1 LED3 NINA_B1_GPIO_8 Blue LED4 NC SW1 NINA_B1_GPIO_7 SW2 NINA_B1_GPIO_18 D0 NINA_B1_GPIO_23 D1 NINA_B1_GPIO_22 D2 NINA_B1_GPIO_21 D3...

Page 23: ...hing of u blox connectivity software is normally done over UART If the flash is erased or any other software is flashed on the NINA B1 module then the SoftDevice and the u blox bootloader must be flas...

Page 24: ...contains the bootloader and SoftDevice 3 Set the correct COM port and the desired speed and click Update button 4 The module will then reboot into the bootloader and the flashing will start A command...

Page 25: ...contains the application Keep in mind that the bootloader will time out and resume the application after 10 seconds Flashing must have started before the time out and resuming of the application 2 3 2...

Page 26: ...x hex When developing and flashing applications based on the Nordic SDK it is recommended to do an Erase all to remove the u blox connectivity software and its stored parameters before flashing down t...

Page 27: ...ng the Bluetooth device address When the new u blox connectivity software is flashed to the module it is important to restore the Bluetooth device address as well Step 1 To enable writing of the Bluet...

Page 28: ...and output pins Accurate design is required to guarantee that the voltage level is well defined during module boot 6 Other pins Accurate design is required to guarantee proper functionality 3 2 Anten...

Page 29: ...minimized to reduce dielectric losses o If traces longer than few centimeters are needed it is recommended to use a coaxial connector and cable to reduce losses o Stack up should allow for thick 50 t...

Page 30: ...o Internal integrated antennas imply physical restriction to the PCB design Integrated antenna excites RF currents on its counterpoise typically the PCB ground plane of the device that becomes part o...

Page 31: ...Select antennas that provide appropriate gain figure that is combined antenna directivity and efficiency figure so that the electromagnetic field radiation intensity does not exceed the regulatory lim...

Page 32: ...igned by an antenna manufacturer providing the best possible return loss or VSWR Provide a ground plane large enough according to the related integrated antenna requirements The ground plane of the ap...

Page 33: ...C connection must be routed through a PCB area separated from sensitive analog signals and sensitive functional units It is a good practice to interpose at least one layer of PCB ground between VCC tr...

Page 34: ...2 H will give tuning capacitors in the range of 130 pF on each pin For good performance match the total capacitance on NFC1 and NFC2 The NINA B1 modules have been tested with a 3x3 cm PCB trace antenn...

Page 35: ...ponents or consider an optional metal shield to reduce interferences that could be picked up by the antenna thus reducing the module s sensitivity An optimized module placement allows better RF perfor...

Page 36: ...re summarized in Table 10 The ESD immunity test is performed at the enclosure port defined by ETSI EN 301 489 1 as the physical boundary through which the electromagnetic field radiates If the device...

Page 37: ...ion Manual UBX 15026175 R09 Design in Page 37 of 49 Compliance with standard protection level specified in EN61000 4 2 can be achieved by including ESD protections in parallel to the line close to are...

Page 38: ...ocal GND and PCB GND Before mounting an antenna patch connect ground of the device When handling the RF pin do not come into contact with any charged capacitors and be careful when contacting material...

Page 39: ...cycles 1 Table 11 Recommended reflow profile Figure 14 Reflow profile Lower value of TP and slower ramp down rate 2 3 C sec is preferred After reflow soldering optical inspection of the modules is re...

Page 40: ...r boards populated with the modules Miniature Wave Selective Solder process is preferred over traditional wave soldering process Hand soldering is not recommended Rework is not recommended Conformal c...

Page 41: ...NINA B1 series System Integration Manual UBX 15026175 R09 Qualifications and approvals Page 41 of 49 5 Qualifications and approvals For regulatory information see the NINA B1 series Datasheet 2...

Page 42: ...n all supported bands such as receiver sensitivity transmitter power levels and so on Figure 15 Automatic test equipment for module test 6 2 OEM manufacturer production test As the testing is already...

Page 43: ...ormed by just scanning for a known Bluetooth low energy device and checking the signal level Received Signal Strength Indicator RSSI These kinds of test may be useful as a go no go test but not for RF...

Page 44: ...2 C Inter Integrated Circuit JSON JavaScript Object Notation LDO Low Drop Out LED Light Emitting Diode MAC Media Access Control MSL Moisture Sensitivity Level NSMD Non Solder Mask Defined PCB Printed...

Page 45: ...d parts for antenna matching PCB layout must be identical to the one provided by u blox please implement one of the reference designs included in this section or contact u blox The designer must use t...

Page 46: ...Should have a solid GND inner layer under and around the RF components vias and small openings are allowed 4 RF trace Antenna coplanar microstrip matched to 50 5 GND trace Green Minimum required top...

Page 47: ...race required around the RF trace and pins GND stitching vias should be used around the RF trace to ensure a proper GND connection No other components are allowed within this area The solid GND layer...

Page 48: ...fications register on our website http www u blox com Revision history Revision Date Name Comments R01 22 Feb 2016 fbro ajoh kgom Initial release R02 19 May 2016 fbro Updated information about reflash...

Page 49: ...m Regional Office China Beijing Phone 86 10 68 133 545 E mail info_cn u blox com Support support_cn u blox com Regional Office China Chongqing Phone 86 23 6815 1588 E mail info_cn u blox com Support s...

Reviews: