Fig. 19
STEP 11: (Electrical connection)
Make the Electrical hookup to the power unit (220V Single Phase).
Important: the wiring must comply with local code. Have a certified electrician make the electrical hook-up to the
power unit. Use separate circuit for each power unit. Protect each circuit with time delay fuse or circuit breaker.
For 208V-230V single phase, use 20 amp fuse.
Warning: Never operate the motor in line voltage less than 208V. Motor damage may occur. Also, Motor
cannot run on 50hz without a physical change to motor.
STEP 12: (Checking running)
Do not place any vehicle on the lift at this moment. Cycle the lift up
and down several times to ensure latches click together and all air is
removed from the hydraulic system. To lower the lift, both latch
releases must be manually released (Fig. 20). Latches will
automatically reset once the lift ascends approximately 17
"
from
base. If latches click out of sync, tighten the equalization cable on the
one that clicks first.
Fig. 20
THE LIFT IS NOW READY FOR USE.
Summary of Contents for TP9KAC
Page 5: ...TP9KF July 2015 A...
Page 20: ...TP9KF July 2015 A PARTS DRAWING Fig A 1...
Page 21: ...TP9KF July 2015 A PARTS DRAWING Fig A 2...
Page 25: ...TP9KF July 2015 A...