4.3. DC wiring 

The series of photovoltaic panels shall be carried out as indicated in section 4.1.  

The cabinet already has the right protections installed for continuous sockets.  

To access the connections, open the back door of the Model H cabinet. It is very 
important to note that each positive must be connected to its negative in the 
cabinet, for this it is recommended to mark the cables or make connections one 
at a time until the installation is complete. 

 

 

 

4.4. AC wiring 

To  connect  Grid,  Back-up  and  Ez  meter  open  the  back  door  of  the  Model  H 
cabinet and connect to the pointed and identified terminals with colors, phase 
gray, neutral blue, yellow and earth green. 

 

 

4.5. Grounding 

Connect ground wire to the ground plate on the grid side, preventing electric 
shock  if  the  original  protective  conductor  fails.  Using  the  auxiliary  connecting 
elements we must connect the grounding, both to the rack and to the structure 
of  photovoltaic  modules.  In  the  panel  and  accessory  box,  20+5  m  (every  3 
panels) of grounding cable is supplied. The 5m are for the connection between 

Summary of Contents for SunBox H

Page 1: ...Instruction manual SunBox Model H...

Page 2: ...nd its complementary technical instructions specifically the ITC_BT 03 04 05 and 40 and the rest of the current regulations either locally or regionally Non compliant use use of the product in applica...

Page 3: ...ons for setting up strings 6 4 2 Preliminary recommendations for installation 6 4 3 DC wiring 10 4 4 AC wiring 10 4 5 Grounding 10 4 5 Recommendations for batteries installation 11 4 5 Commissioning 1...

Page 4: ...o Hybrid Inverter Series Model 5000 48 o Batteries Lithium Series 5 1kWh 2 Description and operation Description The SunBox consists of a mounted and wired cabinet prepared to include up to 2 Turbo En...

Page 5: ...way energy is accumulated for later use at times when energy production is not sufficient 2 When the demand for electricity consumption exceeds the energy produced by photovoltaic panels the Inverter...

Page 6: ...n the end the Inverter performs the energy balancing functions and ensures the operation of the system 2 Back Up mode It is a mode that ensures that when the grid fails the critical loads connected co...

Page 7: ...Wh DoD 90 Cycles at 90 DoD 6000 Manufacturer Cells CATL Cells Metal Can Type of technology LiFePO4 Nominal battery voltage 51 2V Max current Loading Unloading 50A Communication with BMS CAN Batteries...

Page 8: ...ept dry and avoid potentially flooded areas The operating temperature range should be considered which must not exceed 50 C or be less than 0 C Take appropriate measures to ensure the operating temper...

Page 9: ...mm2 hose In case batteries need to be installed the SunBox model H comes ready to store up to 2 Turbo Energy Lithium Series 5 1kWh batteries Its installation is explained below The Network and Back u...

Page 10: ...parate the general loads top of the image and the back up loads bottom Therefore for easier connection and to avoid handling of the connections of the installation loads the following configuration is...

Page 11: ...from causing momentary power outages it is proposed to place an automatic switch that allows network power without going through the SunBox The SunBox Model H is not prepared to withstand excessively...

Page 12: ...l the installation is complete 4 4 AC wiring To connect Grid Back up and Ez meter open the back door of the Model H cabinet and connect to the pointed and identified terminals with colors phase gray n...

Page 13: ...is turned off and has no grid connection 2 Make sure the battery is also turned off 3 Set up battery switches as follows 4 Place the battery in the capsule structure with the corresponding screws 5 I...

Page 14: ...with all connections the machine is ready to commission It will proceed as follows 1 Reset the DC and AC protections at the back of the cabinet 2 Start the Batteries To do this press the Power button...

Page 15: ...iled information refer to the HIS 5000 48 Inverter Manual 6 Security measures To ensure proper installation it is recommended i Use safe mounting tools and install safety devices Use healthy stairs an...

Page 16: ...rent in the presence of solar radiation and verified that the rest of the lines do have contact technical service 8 Troubleshooting Carefully review the content of Page 10 of the Battery Manual Page 2...

Page 17: ...TECHNICAL DATA SHEETS APPENDIX INVERTER CHARGER BATTERIES...

Page 18: ...https www turbo e com Technical data Hybrid Inverter Series 3600 48 and 5000 48 https www turbo e com HYBRID INVERTER WITH BACK UP MODE MAXIMUM CUSTOMER SATISFACTION 5 years...

Page 19: ...artup voltage 150V Max input current A 11A 11A N MPPTs 2 Strings per MPPT 1 1 Output data CA Nominal Power W 3600W 5000W Max Power W 3960W 5500W Peak Power Offgrid Twice the Nominal Power 10S Max Back...

Page 20: ...https www turbo e com Technical data Battery Lithium Series 48V 5 1 kWh LONG LASTING LITHIUM ION BATTERIES MAXUMUM CUSTOMER SATISFACTION PLUG PLAY years 10 years https www turbo e com...

Page 21: ...ting range 48 57 6V Cycle Life 6000 Physical Weight 52 kg Dimensions 475 x 446 x 200 mm Protection class IP20 Battery type LiFePO4 Operation Maximum charge discharge current 50A 0 5 C Temperature oper...

Reviews: