Site preparation - Above ground wiring
Prior to installation of the RTM-75kW, cut
the wiring as per this diagram and crimp
on lugs and bootlace ferrules.
Note:
Drawing is not to scale.
Measure and cut on site.
Cut wiring sheath
480mm from
foundation hole
L2
L3
L1
HP INPUT WIRING & GROUND WIRING
AUX FIELD
WIRING
Cut L3 &
grounding
wire 205mm
from sheath
cut
Cut auxiliary
field wires
470mm from
sheath cut
Cut Input
wiring L1 & L2
185mm from
sheath cut
Trim back all
HP input wires and
grounding wires
to suit M8 lugs (EU)
OR M10 lugs (US)
and crimp on lugs
(not supplied)
Trim back auxiliary
field wires to suit
bootlace ferrules
(not supplied)
ETHERNET
Trim to suit