b.
For a three-phase wye panel (see Figure 4), connect:
•
PowerHawk A terminal to breaker phase A (red wire)
•
PowerHawk B terminal to breaker phase B (black wire)
•
PowerHawk C terminal to breaker phase C (blue wire)
•
PowerHawk neutral terminal to neutral bar in panel (white wire)
•
Earth wire to earth post using lug provided
Figure 4: PowerHawk 120/208V three-phase wye service connection
2.
Replace the front cover of the PowerHawk and secure it in place with the four screws.
3.
If more than one meter is being installed, repeat this procedure for each additional meter.
Earth
Phase A (red)
Phase B (black)
Phase C (blue)
Neutral (white)
AUXA to A
shorting wire
AUXN to N
shorting wire