80
CDHF-SVX01N-EN
Figure 63.
Sequence of operation: ice making: running to ice making
Ice Making Command:
1. Front Panel
2. Tracer
3. External Input
Ice Making
Command
Withdrawn
Evaporator Leaving
Water Temperature
Rises Above the
Differential to Stop
Running
(Ice Building)
Running (Ice to Normal
Transition)
Running
Running
Running
Ice to Normal Transition Timer
(0 to 10 minutes)
Head Relief Request Relay Delay
(1 to 60 minutes)
Head Relief Request Relay Delay
(1 to 60 minutes)
Open IGV at Max Rate/
Max AFD Frequency
Close IGV Min AFD
Frequency
Modulate IGV/AFD
for LWT Control
Ignore Softloading and
Set CLS to 100%
Energize Ice Building
Relay
De-Energize Ice Building
Relay
De-Energize Head Relief
Request Relay
Energize Head Relief
Request Relay
Enforce All Limits and Running Mode Diagnostics