
70
HDWA-SVX001D-EN
Appendix B: Agility
™
™
Chiller Installation Completion
and Request for Trane Service
IIm
mp
po
orrtta
an
ntt:: A copy of this completed form must be
submitted to the Trane Service Agency that
will be responsible for the start-up of the
chiller. Start-up will NOT proceed unless
applicable items listed in this form have
been satisfactorily completed.
TO:
TRANE SERVICE OFFICE:
S.O. NUMBER:
SERIAL NUMBERS:
JOB/PROJECT NAME:
ADDRESS:
The following items
are being installed
and will be completed by:
IIm
mp
po
orrtta
an
ntt:: Start-up must be performed by Trane or an
agent of Trane specifically authorized to
perform start-up and warranty of Trane
®
products. Contractor shall provide Trane
(or an agent of Trane specifically
authorized to perform start-up) with notice
of the scheduled start-up at least two weeks
prior to the scheduled start-up. E
Eq
qu
uiip
pm
me
en
ntt
n
no
ott sstta
arrtte
ed
d b
by
y T
Trra
an
ne
e iiss n
no
ott w
wa
arrrra
an
ntte
ed
d b
by
y
T
Trra
an
ne
e..
Check box if the task is complete or if the answer is
“yes”.
1. A
Ag
giilliitty
y
™
™
C
Ch
hiilllle
err
☐
Installation meets foundation requirements.
☐
In place and piped.
☐
Isolation pads installed.
N
No
otte
e:: Do not insulate the Agility
™
chiller or
adjacent piping prior to the chiller
commissioning by Trane service personnel.
The contractor is responsible for any foreign
material left in the unit.
2. P
Piip
piin
ng
g
Chilled water piping connected to:
☐
Evaporator
☐
Air handling units
☐
Pumps
☐
Flow switch or flow proving device installed (if
not factory-provided)
Condenser piping connected to:
☐
Condenser
☐
Pumps
☐
Flow switch or flow proving device installed (if
not factory-provided)
☐
Cooling tower
Additional piping:
☐
Make-up water connected to cooling tower
☐
Water supply connected to filling system
☐
Does unit have freeze inhibitor? If unit has
freeze inhibitor:
☐
Verify type and concentration correct per
unit submittal
☐
Calculate and record freeze point of the
solution: ___________ (specify °F or °C)
☐
Systems filled
☐
Pumps run, air bled from system
☐
Strainers installed in entering water piping
(evaporator and condenser) and cleaned
☐
Relief valve ventilation piping installed (as
applicable)
3. F
Fllo
ow
w b
ba
alla
an
ncciin
ng
g v
va
allv
ve
ess iin
nsstta
alllle
ed
d
☐
Leaving chilled water
☐
Leaving condenser water
☐
Proper porting to measure flow and balance
4. G
Ga
au
ug
ge
ess,, tth
he
errm
mo
om
me
ette
errss,, a
an
nd
d a
aiirr v
ve
en
nttss
☐
Installed on both sides of evaporator
☐
Installed on both sides of condenser
5. W
Wiirriin
ng
g
☐
Wire size per submittal and NEC 310-16
☐
Full power available
☐
External interlocks (flow switch, pumps
auxiliary, etc.)
☐
Chilled water pump (connected and tested)
☐
Condenser water pump (connected and tested)
☐
Cooling tower fan rotation checked
☐
115 Vac power available for service tools (as
required)
☐
All controls installed and connected
☐
If unit was disassembled for installation
, all
interconnecting wiring reinstalled
☐
For CVHS and CVHM chillers, indicate type of
power distribution grounding:
☐
Solidly Grounded (Center Ground Wye)
-or-
☐
Non-Solidly Grounded (Any Delta, High