Figure 2.6.1b VMC7 and VMC10 Leveling Pad Dimensions
2.6.2 Leveling Procedure:
1.
Set the VMC7 and VMC10 machines on its 4 leveling pads L1, L2, R1, & R2 on a solid, level floor
prepared in accordance with the state and local rules for machine tool installation. For the VMC5,
adjust the level with L1, L3, R1 and R3.
2.
Clean the table thoroughly and place 1 or 2 precision Spirit levels or electronic levels in the center
of the table in the positions illustrated in figure 2.6.2b.
CAUTION!
If using 2 levels, make sure each level is measuring correctly. To check, place the level in one
direction and note reading and then flip 180º and see if the reading is the same. If not, have the
level recalibrated.
3.
On the VMC7 and VMC10, leveling is achieved by using leveling screws R1, R2, L1 and L2. See
figure 2.6.1b. Adjusting screws R3 and L3 should be left loose with the leveling pads and have
no pressure at this time. A 36 mm wrench is required to adjust the leveling bolts.
4.
On the VMC5, leveling is achieved by using leveling screws R1, R3, L1 and L3. See figure 2.6.1a.
Adjusting screws R2 and L2 should be left loose or just snug with the leveling pads and have no
pressure at this time. A 36 mm wrench is required to adjust the leveling bolts.
5.
With the precision levels placed on the worktable as shown in 2.6.2b, level the VMC to within
0.
0005”/10 in.
6.
If the machine must be anchored to the floor, follow the general instruction for installing machine
tools when anchoring.
7.
If the machine must be installed on vibration mounts/pads (rubber, commercially available
leveling and vibration mounts, etc.) follow the instructions delivered with the mounts/pads,