5
7.
To install sheaves, line up drilled holes in bushing with tapped holes in sheaves
and install cap screw.
8.
Align bushing on arbor shaft with bushing on engine shaft and tighten set screw
over keyway.
9.
Tighten (3) cap screw alternately and equally to 10 ft. lbs. of torque and inspect
alignment.
10.
Verify sheave alignment with a straight edge to reaches between the two
sheaves. The sheaves should be aligned with each other to within 1/32”.
11.
Readjust sheave on arbor shaft as required to achieve alignment of writhing
1/32”.
12.
When sheaves are aligned properly, install and pretension belts.
BLADE INSTALLATION/REMOVAL
IF BLADE GUARD IS TO BE REMOVED TO SERICE BLADE,
ITMUST BE REPLACED BEFORE RUNNING SAW. NEVER RUN
SAW WITHOUT BLADE GUARDINSTALLED
1.
Turn lift/lower crank to raise saw. Lock crank in place with locking handle.
2.
Disconnect Spark plug wire.
3.
Remove arbor bolt, lock washer, and outside blade collar with pin.
4.
Clean and inspect arbor, lade, collars and bolts
5.
Verify inside blade collar is fully engaged on arbor and key is positioned
properly.
NOTE: MSC-1 uses 4
”
diameters collars
.
6.
Mount blade over shoulder of
outside collar. Pin must engage 3/8” diameter
hole in blade. Many diamonds blades will have directional arrow on blade.
7.
Re-
Install outside blade collar and blade onto arbor shaft with 1” diameter
shoulder and 3/8” pin engaging inside collar. Install bolt a
nd torque at 60 ft. lbs.
8.
Be sure that blade is installed to rotate in correct direction and that the saw is
set up for required RPM.
9.
Wet cutting diamonds blades must be used with water. Turn water on BEFORE
STARTING CUTTING.