Heat Pump Manual
48
COMMISSIONING
It is important that the heat pump is commissioned in accordance with the guidelines below in
order to ensure proper and trouble free operation.
Outlined below is a check list showing all the considerations that must be taken for the proper
installation and operation of the heat pump
Pre-start checks
Procedure
Carried out in accordance
with procedure?
Notes
Check that there has been no
evidence of damage from
transport
Has adequate clearance been
left around and above the heat
pump as per the instructions
outlined in the installation
section
Check that the isolation switch
has been installed close to the
heat pump in line of sight
On standard heat pumps and
remote condenser models
ensure that the power
connection to the heat pumps
and between the modules is
protected
Note down the pipe run from the
heat pump to the process.
Note down the water pipe sizes
to and from the heat pump
Has the water pipe work been
fitted with insulation
Check the refrigeration circuit
for oil residue and run a leak
detector over the refrigeration
system.
On remote condenser model
note the distance between the
two modules
On remote condensers note the
refrigeration pipe sizes between
the two modules.
Electrical Connection
Isolate power to the heat
pump
and access the electrical
box and check all wiring is tight.