Assembly instructions – Flexible air hose
Air inlet side:
The inlet-side wall connection is supplied separately. Ver-
tical connections must be affixed first. To do this, simply
remove the film on the rear. The cellular rubber can then
be affixed flush with the external edge of the heat pump.
Additionaly the horizontal elements are also lined on the
front. This will help ensure an optimum seal.
Before the machine is positioned on the inlet opening,
check that the wall opening prepared by the customer
has been insulated.
The heat pump may only be moved with
the panels fitted.
If there are any air gaps on the outlet or inlet openings
due to the ground being uneven, this can be corrected
using the adjustable machine feet.
Significant pressure against the wall
should be avoided.
Outlet panels:
The outlet panel is mounted using the four clamps sup-
plied.
Wall flange:
The wall flange must be fitted to the air outlet opening
using suitable mounting materials. There are four bore
holes at the corners of the flange for this purpose.
Hose:
The hose can be cut to any size required. For connecting
the two flanges, the hose insulation is pushed together at
both ends.
The hose is fitted onto the flange using a hose clamp.
The insulation can then be pushed back onto the flange.
The air hose should be supported by a
bracket every 0.5m.