Server Installation and Maintenance
Making Connections
21
Lightspeed G-Series Guide
Power Requirements and Connections
After the server chassis has been physically installed and all other connections made,
connect the two redundant AC power cords to the back of the chassis and to an AC
power source. Be certain to observe the following AC power and connection
requirements and all applicable electrical codes.
The Lightspeed G5 Server is rated at 100-240 VAC, 50-60 Hz, 9.5-4.5 Amps.
These are the detailed specifications:
Take the following precautions to ensure a safe power connection:
•
Make certain that the power source circuit can supply voltage within the specified
range without becoming overloaded.
•
This product relies on the building’s installation for short-circuit (overcurrent) pro-
tection. Ensure that the protective device is rated not greater than 250V, 20A.
•
Counted together, the server and other devices connected to the same power
source must not exceed the total capacity of the power source circuit.
When power is connected, press the Power On/Off (0/1) button on the front of the
chassis to turn the server on. To turn power off, press the Power On/Off button again.
In Rush Current
(On Boot/Idle/Full Load)
Boot
Idle
Full Load
1.6 Amps
1.1 Amps
2.4 Amps
Watts
(On Boot/Idle/Full Load)
Boot
Idle
Full Load
192
132
288
BTU/hr
(On Boot/Idle/Full Load)
Boot
Idle
Full Load
655
450
983