26
OPERATING
6.1 CONTROLS BEFORE COMMISSIONING
Make sure that all the connections have been made properly and sufficiently tight,
respecting the labelling of the equipment.
Check that start up switch of the stabilizer is in «0» or «Off» position.
In equipment’s with the manual Bypass switch option, the preset position from
factory of this switch is «0» (OFF). Turn the Rotary switch to position «2» (Servo).
In case the switch were at position «1» (Mains), turn it to position «2» (Servo).
Check that the loads are shutdown
6.2 START UP AND SHUTDOWN OF THE STABILIZER
6.2.1. First commissioning procedure
It is understood as «Start», that the stabilizer is connected to the electrical mains,
with the correct voltage at the input terminals and the switch turned «On»
In case of three phase load connected to stabilizer check phase sequence correctly.
Check Phase sequence as per below figure.
Chapter
6