6 OPERATION
6.1 Preparing process before start-up.
To make UPS normal and correct running, please confirm the following
items. (Refer to figure 2)
1.Verify electric power switch on back panel is in the ‘OFF” position.
2.Verify the installation place again. (Figure 4 to 10)
3.Rock power cable with hand and see if there is any looseness, if
looseness, retighten the seizure screw.
4.Do not connect load.
5.Inspect input voltage is to meet the demand of UPS (220V±10%) with
ammeter.
6.2 Operation process at first start-up
After verify above items are correct, please start up UPS according to the
following ways:
1.Please switch electric power switch NO FUSE BREAKER (NFB) on the
back panel to the “ON” position. Input indicator light and bypass indicator
light on the front panel are lit on at the same time. As follows figure 15.
Figure 15