3.5.3 Final Installation Checklist
This final installation checklist should be reviewed before starting up the boiler for the first time:
General Boiler Installation
○ Boiler set and level.
○ Clearances to Combustibles maintained.
○ Combustion make-up air provided.
Chimney
○ Appropriate chimney connector installed.
○ Chimney and termination meet requirements.
○ Proper chimney draft.
Plumbing
○ Plumbing fittings tight.
○ Termovar mixing valve or loading unit installed and orientated correctly.
○ Pressure relief valve installed and tested.
Electrical
○ Boiler connected to dedicated 240V, 60 hertz 15 amp power supply.
○ Functional testing performed satisfactory.
○ Dump zone connected.
3.5.4 Combustion and Performance Testing
The boiler should be fired to test for performance, using
Section 4.0
as a guideline.
Provision should be made for dissipating the heat generated.
Have enough fuel to complete an entire testing program.
Verify control strategy
Check that the boiler thermostat is functioning. Check the overheat thermostat, a temporary connec-
tion is made between terminals 6 and 7 on terminal strip Xl
(see circuit diagrams Section 6)
.
The fan
must switch off when the boiler reaches the temperature at which the overheating thermostat is trig-
gered. (The temporary connection between terminals 6 and 7 must be removed when the overheating
thermostat has been checked). The overheat thermostat can be switched on again when the tempera-
ture has fallen by about 60 ºF (15 °C) (about 10-15 minutes). The unlocking knob (H)
(see Fig. 4.1)
is
located under a protective cap.
Test fan by activating reset switch and by having the fan switch in the I position. If the fan does not
turn; insure that the squirrel cage (fan blades) are not hitting mounting bolts located on the inside of
fan housing. Re-adjust the squirrel cage if needed.