![Tarm Biomass SOLO INNOVA 30 Installation And Operation Manual Download Page 23](http://html.mh-extra.com/html/tarm-biomass/solo-innova-30/solo-innova-30_installation-and-operation-manual_819831023.webp)
Solo Innova Instructions 1-800-782-9927 Version 01-18
Tarm Biomass · 4 Britton Lane · Lyme, NH 03768
9
Install Right Front Corner Zip Strip
Zip Strip Can
Bend if Needed
Boiler Installation & Start-up > Setting the Boiler
Page 19
Remove 4
Screws
Remove the connector panel and wire
harness on the back of the boiler by re-
moving the four screws.
This shows the back panel with the con-
nector panel removed.
Mount the new electrical box over the connec-
tor slot. Fish the connector wires through the
slot.
Mounting
screws go here.
Mounting
screws go here.
10
11
12
If the junction Box is already mounted;
Please skip to Step 13.