6. Commissioning
6.1 Construction
•
Ensure that there are no foreign bodies inside the device, and that all the components are
securely in place.
•
Manually check that the fan does not come into contact with the sides.
•
Make sure that mounting bolts or duct do not interfere inspection panels.
•
Make sure that all service doors and panels are closed and fastened.
•
Make sure that all connections are made correctly.
•
Check that the inspection flap is closed.
•
Ensure that ALL connections are properly made.
6.2 Electrical connection
•
Fans
CAUTION!
All installation work must only be carried out by qualified and authorised personnel
using suitable equipment.
The client and/or the installer of the electric system is responible for choosing
the equipment and cables used for connecting the fan electrically, based on
the dimensions of the motor installed and the characteristics of the main
power supply.
Depending on the level of automation offers the following options:
•
Without management – all consumers and equipment (sensors, pressure switches, electric
actuators, etc.) are displayed on the terminals, ordered in the electrical board. – fig4
Summary of Contents for EVB - HiE
Page 2: ...Rev 2013 08 25 01 1 ...
Page 19: ...Rev 2013 08 25 01 18 ...
Page 20: ...Rev 2013 08 25 01 19 ...
Page 23: ...Rev 2013 08 25 01 22 9 2 Identification plate ...
Page 26: ...Rev 2013 07 25 01 25 ...
Page 27: ...Rev 2013 07 25 01 26 ...
Page 28: ...Rev 2013 07 25 01 27 ...