![Tailift TPR720A Operation Manual Download Page 24](http://html1.mh-extra.com/html/tailift/tpr720a/tpr720a_operation-manual_3265689024.webp)
4-4
4.3 Installation of the machine.
4.3.1 Have the machine set onto the fastening bolts of the crate base.
(1) Tools
Sling, lifting equipment, spanner, movement plate, insertion blocks and level
adjusting blocks.
(2) Procedure
a. After dismantling the wooden crate, get the manuals and tool box out.
b. Remove the fastening bolts.
c. Hook it using sling, lift it up and move to site for installation.
d. Align the ground bolts and the base bores and set the later onto them.
Meanwhile, have the level adjusting blocks inserted to the underneath of the level
adjusting bolts.
e. Remove the lifting equipment and slings.
f. Have nuts for the ground bolts mounted.
Summary of Contents for TPR720A
Page 7: ...1 6 Arm elevating motor For TPR 720A TPR 820A TPR 920A Arm elevating motor For TPR 1100...
Page 30: ...5 4 5 1 2 For TPR 1100 The front view of TPR 1100...
Page 40: ...5 14 Examples of clamping using the universal clamp...
Page 81: ...9 6 9 6 Electrical Circuit Diagram For TPR720A TPR820A TPR920A Standard...
Page 84: ...9 9 9 8 Electrical Circuit Diagram For TPR1100 Standard...