8
Commissioning
8.1
Preconditions
•
Mounting and electrical connection have been correctly performed.
•
Installation residuals and foreign objects have been removed from the fan.
•
Inlet and outlet are free.
•
The safety devices have been fi tted (protection against contact).
•
Grounding connected.
•
The cable glands are tight.
•
Provided mains connection complies with the data on the name plate.
•
Nominal current (from the name plate) does not exceed the mains data.
8.2
Commissioning
WARNING
Hazard from electrical voltage!
»
Commissioning by trained and instructed qualifi ed personnel only!
Switch the circular duct fan on as planned.
WARNING
Hazard from bursting parts!
»
»
When checking the direction of rotation, wear safety goggles.
Check:
–
the direction of rotation / conveying. The direction of rotation always applies looking at the rotor.
–
smoothly running
Check, if safety elements e.g. protective guards are fastened.
9
Operation
9.1
Safety notes
WARNING
Hazard from electrical voltage!
»
The device may only be operated by persons
–
instructed in function and risks,
–
who have understood handling and can accordingly react.
»
Ensure that children cannot operate or play with the device without supervision.
»
Ensure access only to persons, who can safe handle the device.
9.2
Operating conditions
•
Do not operate the circular duct fan in an explosion-hazardous atmosphere.
•
During operation, touching the rotor must not be possible.
•
Safety components must not be bypassed or put out of function.
•
The circular duct fan may operate inside limits declared on the nameplate.
•
Prevent suction of foreign particles, this can destroy the fan.
•
Sound development can be reduced by using a sound fi lter.
29
Commissioning
Summary of Contents for prio 160 E2
Page 50: ...50 Systemair GmbH...
Page 52: ...52 1 1 1 ATTENTION 1 1 1 1 1 2 1 2 3 1 2 prioAir...
Page 54: ...54 2 4 prioAir 3 4 4 1 prioAir prioAir 4 2 prioAir...
Page 55: ...55 prioAir 07 2014 4 3 1 prioAir 5 5 1 prioAir EC prioAir E2 EN 13779 EC...
Page 56: ...56 5 1 1 5 4 3 1 2 2 prio 200 EC 1 4 2 5 3 6 7 3 4 1 5 2 3 prio 200 E2 1 5 2 6 3 7 4...
Page 59: ...59 prioAir 07 2014 6 3 1 7 5 prioAir E2 4 prioAir E 5 1 Befestigungswinkel...
Page 62: ...62 10 5 10 1 Systemair Systemair Systemair Systemair 2 9 3...
Page 63: ...63 prioAir 07 2014 10 2 5 10 3 Systemair 10 4...
Page 64: ...64 11 5 12 12 1 12 2...