18/55 |
S-BA2
Product Handling
Warning
Some damper parts can have sharp edges. To prevent injuries, use gloves when you install or move the damper. If
you use or operate the damper incorrectly, there is a risk of:
- electric shock.
- fire.
- other damage.
Ensure that installation is performed by a trained person. The S-BA2 is made of boards and sheet metal. Thus
considered fragile. Be careful when you move the smoke control damper. Two persons are necessary to move the
smaller dampers and put them in the installation opening. It is necessary to move the bigger dampers with suitable
lifting equipment (forklift, crane). Please follow both textual and graphic instructions.
1. Unpacking:
• Remove the packaging
• Remove the grille (if installed).
2. Functionality check:
• Unscrew two screws from mechanism cover.
• Pull the textile eyelet.
• Remove the mechanism cover.
• Perform damper's functionality check (see "Operation Manual" section).
3. Electrical connection:
• Make a hole in the rubber crossing for the wires as needed in top or bottom.
• Push the wires through the rubber crossing.
• Insert the mechanism cover back into its place.
• Fix the mechanism cover by previously removed screws.
4. Placing the damper:
• Prepare the opening and/or duct connection surfaces as per the desired installation type.
• Carefully lift the smoke control damper with the forklift, crane or manually.
• Place the damper in the opening or on duct connection surfaces.
5. Fixing the damper:
NOTE: Make sure to continually check the alignment of the damper against the supporting construction, opening or
against the duct connection when performing the next steps.
• Fix the damper with supporting construction using suitable screws through the blade endstop. For duct installations
fix the damper using duct flange connections.
• Verify there is no skewing of the damper body by measuring diagonal dimensions of the blade area or the nominal
dimension.
• As per chosen installation add filling to the gap between the damper body and the opening. For duct installations
perform insulation arround damper.
6. Finishing:
• Clean the damper from the debris and excess material from the filling or insulation.
• Perform damper's functionality check (see "Operation Manual" section).
• Connect the continuous duct or mount the removed grille.
• Create and/or fill out the Operating Journal included with the smoke control damper (Operating Journal can be also
downloaded at design.systemair.com)