SYMEO Local Positioning Radar System
LPR®-1D24
LPR®-1D24 Station
– Overview and Mounting
Mounting and Alignment of LPR®-1D24 Units
Copyright © SYMEO GmbH 2015
LPR-1D24_Users_Manual_FCC-IC-Edition_EN.docx
Page 11 of 34
3.1
Mounting of the Fall Protection
The LPR
®
-1D24 units must be protected against fall. For every unit Symeo provides a
protection set consisting of the following components:
A: 2 x ring nuts M5,
B: 2 x snap hooks 5 x 50 mm
C: 1 x steel cable 3 mm x 1 m
The two ring nuts must be mounted on the back of the LPR
®
-1D24 unit laterally on the
respective second screw from above, which are 4 mm longer than the other screws. Then
the snap hook must be attached to the ring nuts. Please put the steel cable around a pipe or
a bracket and hang it also in the snap hook (see picture below).
The backup set should be installed before the assembly of the unit to
secure it against falling.
C
A
B
Figure 3: Mounting of the fall protection