Starting instructions
Page 35/40
Installation and starting instruction manual
SYCLOPE TRACE’O
®
Calibrate the pH value
►
Repeat this same process for all the other settings.
Calibration via the “calibration” button can only be performed while the treatment is in
process (Stop/Start LED lit and not flashing).
8)
Start processes and dosages
Once you have made entered all the preceding settings, you are ready to begin processing and dosing
by means of the
SYCLOPE TRACE’O
®
controller.
Before beginning processes, please make sure that all the parameters and various safety
features mentioned in this documentation have been observed.
►
To begin processes, press the key
►
Check that everything works and that the controller begins the treatments as required.
The LED of the “
STOP/START
” button can have various statuses according to the
environment.
Lit: the processes are active
Not lit: the processes are inactive
Flashing: the processes are paused if a “
start delay
” is programmed or if the
conditional optional functions “CAD” and “Flsw” are active or if an operating
interval timer has been defined and when the controller is out of this interval.
To assist the user in managing the treatment of the water, the
SYCLOPE TRACE’O
®
controller is
equipped with visual indications directly on the screen for alarms exceeded and for injections of
chemical products, and some LEDs on the front panel.
_
>> USER MENU <<
_
Calibrations
Free chlorine
pH
Flow rate
_
>> USER MENU <<
_
Calibrations
Free chlorine
pH
Flow rate
_
Main parameter
_
Calibrations
Zero (or pH=7)
Slope (or Gain)
Clearing ...
_
Main parameter
_
Calibrations
Zero (or pH=7)
Slope (or Gain)
Clearing ...
Reference: 7.01 pH