To install the SuperServer 5019S-WR into a Telco (or “open”) type rack, use two L-shaped
brackets on either side of the chassis (four total).
1. First, determine how far the server will extend out from the front of the rack. The chassis
should be positioned so that the weight is balanced between front and back.
2. Attach the two front brackets to each side of the chassis, then the two rear brackets
positioned with just enough space to accommodate the width of the rack.
3. Finish by sliding the chassis into the rack and tightening the brackets to the rack. See
Figure 2-4.
Figure 2-4. Installing the Server into a Telco Rack
Figure 2-3. Installing the Server into a Rack
Note:
Figure is for illustrative purposes only. Always install servers to the bottom of a rack first.
2.4 Installing the Server into a Rack
Installing to a Standard Rack
You should now have rails attached to both the chassis and the rack. The next step is to
install the server into the rack.
1. Line up the rear of the chassis rails with the front of the rack rails.
2. Slide the chassis rails into the rack rails, keeping the pressure even on both sides (you
may have to press the locking tabs when inserting). See Figure 2-3.
3. When the server has been pushed completely into the rack, you should hear the locking
tabs "click".