7.Troubleshooting

7.1 Fault Messages

Sunways STH 4~12kW series three-phase hybrid inverter is designed in accordance with 
gridoperation standard, and conform to the requirements of the safety and EMC. The inverter 
had passed a series of rigorous tests to ensure it runs sustainably and reliably before shipment. 
When a fault occurs, the corresponding fault messages will display on the OLED display, and in 
this case, the inverter might stop feeding into grid. 
The fault messages and their corresponding troubleshooting methods are listed below:

Error Message

Solution

Mains Lost

1. Check whether the mains supply is lost.

2. Check whether the AC breaker and terminal are well connected.

Grid Voltage Fault

1. Check whether the impendence of the AC cable is too high to lead the grid 

voltage increased. Change a thicker AC cable if it is.

2. Extend the voltage protection range if it is allowed by the electricity 

company.

Grid Frequency Fault

1. Check whether the AC cable is correct and well connected.

2. Change to another country with wider protection range if it's allowed by the 

local electricity company.

DCI Fault

1. Restart the inverter.

2. Seek for help from the installer or manufacture.

ISO Over Limitation

1. Restart the inverter.

2. Seek for help from the installer or manufacture.

GFCI Fault

1. Restart the inverter.

2. Seek for help from the installer or manufacture.

PV Over Voltage

Reduce the number of PV panels to make sure the open-circuit voltage of 

each string is lower than the inverter max allowed input voltage.

Bus Voltage Fault

1. Check whether the input voltage is over the limitation.

2. Seek for help from the installer or manufacture.

Inverter Over Temperature 1. Check whether the input voltage is over the limitation.

2. Seek for help from the installer or manufacture.

SCI Fault

1. Restart the inverter.

2. Seek for help from the installer or manufacture.

SPI Fault

1. Restart the inverter.

2. Seek for help from the installer or manufacture.

E2 Fault

1. Restart the inverter.

2. Seek for help from the installer or manufacture.

GFCI Device Fault

1. Restart the inverter.

2. Seek for help from the installer or manufacture.

AC Transducer Fault

1. Restart the inverter.

2. Seek for help from the installer or manufacture.

Relay Check Fail

1. Restart the inverter.

2. Seek for help from the installer or manufacture.

Flash Fault

1. Restart the inverter.

2. Seek for help from the installer or manufacture.

7.2 Maintenance

Risk of inverter damage or personal injury due to incorrect service!
Always keep in mind that the inverter is powered by dual sources: PV strings 

and utility grid.
Before any service work, observe the following procedure.

1.Disconnect the AC circuit breaker and then set the DC load-break switch of the 

inverter to OFF;

2.Wait at least 5 minutes for inner capacitors to discharge completely;

3.Verify that there is no voltage or current before pulling any connector.

Keep non-related persons away!
A temporary warning sign or barrier must be posted to keep non-related 

persons away while performing electrical connection and service work.

Restart  the  inverter  only  after  removing  the  fault  that  impairs  safety 

performance.
As the inverter contains no component parts that can be maintained, never 

arbitrarily replace any internal components.
For any maintenance need, please contact Sunways. Otherwise, Sunways shall 

not be held liable for any damage caused.

Servicing of the device in accordance with the manual should never be 

undertaken in the absence of proper tools, test equipment or the latest revision 

of the manual which has been clearly and thoroughly understood.

Attention

Note

Danger

Caution

Items

Methods

Period

System clean

Check the temperature and dust of the inverter. 
Clean the inverter enclosure if necessary.
Check if the air inlet and outlet are normal. 
Clean the air inlet and outlet if necessary.

Six months to a year (it depends on the 

dust contents in air.)

Summary of Contents for STH-10K-HT

Page 1: ...1 Three phase High voltage Hybrid Inverter STH 4K 5K 6K 8K 10K 12KTL HT User Manual Ningbo Sunways Technologies Co Ltd...

Page 2: ...e 16 3 4 Packing List 17 4 Product Installation 18 4 1 Selection of Installation Location 18 4 2 Mounting the Inverter 19 4 3 Electrical Connection 21 4 4 Communication Connection 34 4 5 Monitoring De...

Page 3: ...n and maintenance 2 1 6 To use this grid connected inverter for power generation needs the permission of the local power supply authority 2 1 7 During the operation of the inverter the surface tempera...

Page 4: ...e symbols displayed on the hybrid inverter nameplate and packing box 2 4 1 Symbols on the Hybrid Inverter Description Symbol Grid status indicator 2 4 2 Symbol on the Inverter nameplate The inverter c...

Page 5: ...d below STH 4KTL HT STH 5KTL HT STH 6KTL HT STH 8KTL HT STH 10KTL HT STH 12KTL HT 3 1 3 Applicable grid type The applicable grid types of the Sunways STH 4 12kW series are TN S TN C TN C S and TT When...

Page 6: ...in in if the battery is not enough Mode 2 In this working mode set the Pmax from grid in the App can realize the Peak Load Shifting When the loads consumption less than the Pmax loads are supplied by...

Page 7: ...ge the battery in the predetermined period Inverter will use power from PV and battery to supply loads in the predetermined period and the insufficient part will be supplied by the grid No Grid No Gri...

Page 8: ...ure 3 4 410mm 175mm Name Plate Logo Display 550mm 410mm Figure 3 5 Bottom view Figure 3 6 Inverter back view 3 2 3 Inverter bottom view as shown in Figure 3 5 3 2 4 Inverter back view as shown in Figu...

Page 9: ...the display Red An alarm or fault is detected view the fault info on the display 5 Display On Display the inverter operation information Off Display off to save power press the button to wake up the d...

Page 10: ...ectly to strong sunlight to prevent the power derating due to excessive temperature 4 The inverter should be installed in a place with shelter to prevent direct exposure to sunlight and rain 5 Install...

Page 11: ...ning 4 3 Electrical Connection Danger hint A high voltage in the conductive part of the inverter may cause an electric shock When performing any installation on the inverter make sure that the AC and...

Page 12: ...2 L1 CT C CT B CT A PV Strings Battery To Battery To Sunways Meter Power Meter Sunways Meter AC Breacker AC Breacker AC Breacker AC Breacker AC Breacker 1 phase Loads 3 phase Loads Loads FN Set Run Ac...

Page 13: ...stem all inverters PE wire need to be connected to the same grounding copper bar to ensure equipotential bonding 4 3 2 External ground connection Ground terminal connection steps 1 The external ground...

Page 14: ...o the corresponding positive and negative connectors pull back the cable to ensure that the terminal is tightly attached in the connector 6 Use an open end wrench to screw the nut to the end to ensure...

Page 15: ...ered when making AC output connection 1 An independent AC breaker is required in both inverter on grid and back up output side and any loads cannot be connected with inverter directly 2 Before making...

Page 16: ...ence as shown in Figure 4 23 Strip Length 8mm 40 60mm Wire Diameter 12 18mm Cables Screw cap The insulator AC sheet cover BACK UP ON GRID Single hole seal ring Figure 4 25 Figure 4 26 Figure 4 24 3 Pu...

Page 17: ...S1 10 L3 S2 12 L Power supplied from 220V grid 13 N RS485 RS485 Communicate with inverter CT installation direction and phase sequence should strictly follow the instruction in the user manual otherw...

Page 18: ...on bus interface EMS EMS power dispatching interface RLYOUT Dry contact output a group of normally open contact passive dry contact PARCAN EMS RLYOUT 4 4 2 Communication between inverter and meter The...

Page 19: ...ake sure the battery you selected is in the battery approval list of Sunways otherwise the system may not work properly Please contact your installer or Sunways service team for confirmation if you re...

Page 20: ...the installation represents that the assembly is in place 5 Start and Stop 5 1 Start Inverter When starting the inverter follow these steps 1 Turn the DC switch in the inverter bottom to the ON positi...

Page 21: ...te and Local before starting the auto test Remote is set as 1 by default which only can be modified to 0 by sending an external command and Local is set as 0 by default which can be modified to 1 thro...

Page 22: ...e installer or manufacture SPI Fault 1 Restart the inverter 2 Seek for help from the installer or manufacture E2 Fault 1 Restart the inverter 2 Seek for help from the installer or manufacture GFCI Dev...