Important information
· The direct PV generator voltage is availa-
ble internally after connecting the PV
generator to the solar inverter via the
DC connectors and switching on the PV
generator switch!
· Please note that the input capacitors are
still charged even after switching off the
PV generator switch or removing the PV
generator plug connection!
· After disconnecting the AC and DC side,
the solar inverter still conducts voltage
for up to ca. five minutes!
· Therefore, wait for at least five minutes
until the internal voltage has dissipated.
Then you can work on the terminals!
Note chapter 2.1 «Safety information»!
· The DC voltage can be up to 850 V. The
unit may only be opened by a qualified
electrician!
· Always disconnect the PV generator side
first by opening the PV generator switch,
and then the grid connection by isolating
the relevant mains fuse!
· If you do not have a PV generator switch
in your PV system, you must disconnect
the grid connection first of all by isola-
ting the relevant mains fuse. However,
an error will be entered in the error
memory of the solar inverter!
· Disconnection of the PV generator by
removing the Tyco Solarlok DC con-
nectors must never be performed under
load. In the event of non-compliance,
the connectors could be damaged by a
strong electric arc. In this case, the rele
vant connectors must be replaced!