4
1.12 MOVING MACHINE SAFELY
1)
Before the machine travels and swings, operator should know
the position of other people.
2)
When machine travels or before it swings, operator should
warn other people by ringing the horn.
3)
Operation at confined area, should use signal in swinging,
and harmonize the hand signal before machine start-up.
4)
Before operate the machine traveling, must confirm that the
operation of traveling pedal/control lever should be
corresponding with the traveling direction.
5)
Treadle the foreside of traveling pedal or push traveling lever
forward, and the machine will travel along tension wheel. By
contraries, the machine will travel along sprocket wheel.
6)
When machine travel on slope, place bucket as figures
showing, keep bucket 200-300mm up the slope ground,
if the machine slides or becomes unstable, set the bucket
down at once(As figure 1.12).
1.13 PREVENTING ACCIDENTS WHILE BACKING OR SWINGING
1)
In order to prevent accident while backing or swinging, the
operator must follow:
2)
Before back or swing the machine, look round and confirm
nobody is around.
3)
Ensure that other people standing out of the boom swing
range.
4)
Pay attention to that whether other people stay in work range
or not. Ring horn or use other signal to warn before move the
machine.
5)
If the operator’s vision is blocked when the machine backs, a signalman is needed and the signalman
should always be seen.
6)
If signalman needed, the signalman should use hand signal. Only when both signalman and operator
understand the meaning of signal, the operator can operate the machine traveling and swinging (As figure
1.13).
Figure 1.12.1
Figure 1.12.2
Figure 1.13
Summary of Contents for SWE50B
Page 24: ...17 2 1 CAB As figure 2 1 shown Figure 2 1...
Page 38: ...31 No step on label...
Page 92: ...85 5 4 11 Hose...
Page 119: ...112 Engine Fault Diagnosed Code...
Page 120: ...113...
Page 121: ...114...
Page 129: ...122 6 1 4 Circuit Diagram 2R 2RL 2B FUSE 100 F 50V 100 F 50V motor sw motor relay FUSE B G R...
Page 131: ...124 6 1 6 Hydraulic Diagram...
Page 136: ...129 6 2 4 Circuit Diagram 2R 2RL 2B FUSE 100 F 50V 100 F 50V motor sw motor relay FUSE B G R...
Page 138: ...131 6 2 6 Hydraulic Diagram...
Page 143: ...136 6 3 4 Circuit Diagram...
Page 145: ...138 6 3 6 Hydraulic Diagram...
Page 150: ...143 6 4 4 Circuit Diagram...
Page 152: ...145 6 4 6 Hydraulic Diagram...
Page 157: ...150 6 5 4 Circuit Diagram...
Page 159: ...152 6 5 6 Hydraulic Diagram 280...
Page 164: ...157 6 6 4 Circuit Diagram...
Page 166: ...159 6 6 6 Hydraulic Diagram...
Page 171: ...164 6 7 4 Circuit Diagram...
Page 173: ...166 6 7 6 Hydraulic Diagram...
Page 178: ...171 6 8 4 Circuit diagram...
Page 185: ...178 6 9 4 Circuit Diagram...