ТЕХНИЧЕСКИ ПАСПОРТ. ИНСТРУКЦИЯ за МОНТАЖ и ЕКСПЛОАТАЦИЯ
ТЕХНИЧЕСКИ ПАСПОРТ. ИНСТРУКЦИЯ за МОНТАЖ и ЕКСПЛОАТАЦИЯ
INSTALLATION and OPERATION MANUAL
INSTALLATION and OPERATION MANUAL
In this case, you should contact
an authorized specialist to
determine where the problem is
and restart the unit.
5.6 High pressure protection system
To prevent system malfunction due to
high pressure, a sensor is installed that
stops the device from operating in case of
exceeded set-up.
5.7. Work conditions.
The flawless operation of the thermody
-
namic pump is guaranteed at an ambient
temperature of -70 ° C and 40 ° C. The air
must be clean with an average humid-
ity that must not exceed 50% at 40 ° C.
At lower temperatures, the average air
humidity may be higher. Instruments in-
stalled at high altitude may operate with
reduced efficiency due to lower atmo
-
spheric pressure.
6. INSTALLATION
THE THERMO-PUMP TDA
The minimum height of the room in which
the thermodynamic boiler can be in-
stalled is
- 2000 mm for TDA E200 and TDA S200
models
- 2300 mm for TDA E300 and TDA S300
The product is designed to draw air from
the environment or from another room
through air ducts. At the same time, the
outgoing cooled air can also be transport-
ed to a room or turned into the environ-
ment.
6.1. Installation and installation site.
- The TDA is always installed indoors on a
flat surface that can support the weight of
the product itself and its contents. Ensure
access to the flange, anode, and electric
heater for uninterrupted maintenance
and repair. The allowable minimum dis-
tance is shown in the diagram below.
- Do not place the product near flamma
-
ble gases, acidic or corrosive materials
that could damage its components during
installation / repair.
- Ensure that a drainage system is installed
at the installation site, adequate to the
boiler volume.