5. Commissioning
5.1. Startup / Shutdown Procedure
The inverter must be installed by a qualified / licensed electrical engineer in accordance to the countries
wiring regulations.
Only after the engineer has completed the Earth Bond, RCD, and Earth Leakage Tests, check the solar
panel Voc voltage (Must not exceed 480V) and check the battery voltage. Then, the inverter can now be
switched on.
Power on Sequence:
1. Switch on AC
2. Press Start Button
3. Switch on Battery and battery breaker
4. Switch on the DC (PV Isolator)
Shutdown Sequence:
1. Switch off AC
2. Press the start button
3. Switch off the battery and the battery breaker
4. Switch off the DC (PV isolator)