User Manual
7 Commissioning
39
Step 10
Configure time according to the local
time. Time setting is very important, which
directly affects data logging.
Press
to
move cursor and
Press
to scroll up time
value. Confirm the settings by
Pressing
ENTER
.
Step 11
After configuring all parameters, there
will be a “Setting confirmation” screen.
Check
whether
all
above-mentioned
parameters are correct. Confirm by
Pressing
ENTER
. Cancel by
Pressing
ESC
and reset.
Step 12
Inverter will enter into startup process.
Observe status of LED indicators and the
LCD
main
screen.
If
inverter‘s
commissioning
succeeds,
the
“RUN”
indicator will be lit and “RUN” will be
displayed on the “State” area.
If inverter’s commissioning fails, the “FAULT” indicator will be lit and “fault” will
occur on the display. Press
to view “current fault” information. Remove the
existing fault and then repeat starting up inverter as the above procedures.