Installing the Server
37
FIGURE:
Unlocking the Slide Rail Assembly
3. If the server cables have been placed inside the CMA, inspect them for binding
or kinks.
4. Slowly pull the server out of the rack until the slide rails reach their stops.
5. Verify that the CMA extends fully and does not bind in the slide rails.
6. Verify that the server extends fully and locks in the maintenance position.
The server should stop after approximately 15 in. (40 cm) of travel.
7. Pull both slide rail release buttons toward you simultaneously and slide the
server back into the rack.