22
Free-AIr-3-IN
EN/02.2018 © STULZ SpA – all rights reserved
CONNeCTION AND POSITIONING OF TeMPerATUre PrOBeS
INFOrMATION
Free-Air-3-IN units are provided with 2 PTC probes: S1 for internal temperature, S2 for external
temperature, supplied loose. Their cables are 8 m long with minifit termination on one end. Must
be positioned suitably and connected during installation, as follows.
1. Place internal air temperature S1 so that it can measure average temperature conditions inside
the room. Recommended position: at 2m height away from cold air flows from any cooling device.
2. Connect the probe S1 to X13 connector of the board C102.
6. Start-up
INFOrMATION
Before you first start up the system install and connect it up as described in the "Installation"
chapter.
Two keypads are available for C102: ACTKPDC1010H is a 4x20 display and is necessary for
the start-up of the units. Only this keypad allows full access to all parameters. ACTUKPD is a
keypad with 3-digit display for user functions, such as set points setting, alarm display and reset,
counters display.
In this chapter TI = internal temperature; TAE = external air temperature.
• Make sure the main switch is turned off and that the system is isolated from power mains.
• Check that all power switches and control fuses in the electric system have been turned off.
• Double check that the main electrical supply cable and the terminals, including the PE terminals,
are correctly hooked up.
• Check that contactors are free to move.
• Double check if signal cables are correctly connected and fastened to the electrical terminals of
the unit (according to wiring diagram).
• Double check correct positioning and fastening of temperature probes.
6.1. Controller setting
• Close all unit panels.
• Use the main switch to turn the FCL on.
• Activate automatic switch on 48V DC power supply line.
• Check software version loaded on C102 controller on one of the main screens of display.
6.2. Functional checks
• At this point the electronic board is powered and individual components can be enabled to check
they work properly. Software of C102 includes a semi-automatic test procedure to be used during
the start-up. For a detailed description of every function of C102 electronic controller, please
consult its specific manual.