2.3 transport
danger
Mortal danger by crushing
A defective lifting device can lead to the uncontrolled fall of the chiller unit.
Do not stay under suspended loads!
The Stulz chiller units can be lifted and moved by lifting devices with ropes or belts
.
• take care that the unit is in an upright position at the transport.
Clamps to lock
the rope or belt
construction sizes 3 and 4
For the transport, there are openings in the base frame, through which steel tubes must be pushed.
The steel tubes are not delivered and must be provided by the customer.
requirements for the steel tubes:
Length:
minimum 1600 mm
Diameter:
< 50 mm, according to unit net weight
Wall thickness: according to unit net weight
To prevent the ropes from sliding off the steel tubes, fasten a clamp at
the end of the tubes.
Position of the clamps: maximum 100 mm distance from the base frame
The lifting device must consist of one (size 3) or two cross beams, with a
minimum length of 1400 mm.
The drawings on the following pages show the dimensions for the sus
-