![SteppIR DB11 Yagi Assembly Manual Download Page 25](http://html.mh-extra.com/html/steppir/db11-yagi/db11-yagi_assembly-manual_1372689025.webp)
22
2112 116TH AVE NE SUITE 1-5, BELLEVUE WA, 98004
WWW.STEPPIR.COM
TEL: (425)-453-1910 FAX: (425)-462-4415
FINAL ANTENNA TEST
At this point the antenna should be 98% completely assembled and ready to be secured to the tower. Before
this is done the antenna relays must be tested to insure that the antenna will operate correctly. This is very
critical for the antenna to be able to switch each of the EHU’s from passive to driven when needed. If wiring
was done incorrectly then the relays will not switch at the correct time, if at all. Follow the below test proce-
dure to insure the antenna is wired correctly.
This test should be conducted while the antenna is on the ground. The controller will need to be connected
to the antenna and also plugged into the power supply. In additions, the wire terminals will need to be
exposed from the terminal housing at the middle of the boom. In the case of the connector junction box it
may help to wait to install the lid of the connector box, for ease of testing. The coax antenna switch box lid
should not have been installed yet either. The wire terminal on the coax antenna switch will need to be
exposed to complete this test. Follow
figure 14
and
figure 15
for completing the final wiring test.
Figure 14
NORMAL MODE Relay Test
NOTE:
During the test you do not need to
unscrew any of the terminals. All
voltages can be pulled off of the
screw head of the testing terminal.
Polarity does matter for testing the
voltage. The voltage present will be
slightly less then the supply voltage
(24v or 33v DC, depending on
which power supply option you
have).
Testing Procedure:
With the controller plugged in you
will first need to tune the antenna to
anywhere within the 20m band.
Make sure that the antenna is in the
“NORMAL MODE”.
Once the red TUNING LED light
has stopped flashing on the con-
troller, perform the 3 different tests
shown to the right.
This would also be a good time to
listen to the elements while they are
moving.
Ensure that all the elements are
running smoothly and no stalling
occurred as the copper elements
move through the sweeps.
+
-