5.4 Overload Condition
The working principle of the UPS when overloading is illustrated as follows
:
(1) Generally, modern electronics & IT equipment generate an inrush current
when switching on. The amount of inrush current varies from equipment to
equipment, some can be as high as 6 times its rated capacity while others
produce negligible inrush. To prevent severe damage to the Inverter, caused
by inrush produced by loads, the UPS is equipped with an electronic overload
protection feature. If the UPS load is >105~120% of its capacity, it will switch
to bypass mode in 30 seconds to protect the Inverter. If the overload condition
is eliminated by reducing the load to <105%, the UPS will switch back to
Inverter mode automatically. If the UPS is over 150% loading, it inverter will
shutdown immediately.
Summary of Contents for UniStar C
Page 1: ...Form No 003 2308 Rev C 1K 2K 3K UniStar C Intelligent True On Line UPS User Manual ...
Page 9: ...8 3 2 Rear Panel Descriptions 120V 1KVA 10 8 7 1 2 3 5 4 6 2KVA 3KVA ...
Page 19: ...18 4 3 Set up Tower Configuration Setup Step 1 Power Module Battery Module Step 1 ...
Page 20: ...19 Rack Mount Configuration Setup Step 1 Step 2 Step 3 ...
Page 21: ...20 Step 4 Step 5 ...
Page 27: ...26 Q1 Q2 R1 R2 S ...
Page 28: ...27 T U1 U2 U3 V ...
Page 32: ...31 4 4 3 Battery Replacement Step 1 Step 2 ...
Page 33: ...32 Step 3 Step 4 1KVA 2K 3KVA ...