Triple Rail Slide Plan:
The Triple Rail Slide connects to the deck via a plastisol coated
connector plate. The connector plate attaches to the top of the
deck holes which are 15” apart on center. The slide legs are
attached to the underneath of the exit end of the slide.
INSTRUCTIONS:
1. Mark 2 ground holes for the slide legs by placing the
slide onto the deck, spray paint the ground to mark leg
positions, and then remove the slide. (the legs are not
attached to the slide yet)
2. Install the slide leg on the bottom of the slide with (3)
3/4” x 3/4” button head bolts. See Detail 3.
3. Install the slide with legs attached into the ground holes
first, then to the deck.
4. Re-bar goes through the holes in the bottom of the legs.
5. The connector plate attaches to the deck when it is 90
degrees to the deck and any adjustments have been
made to the ground holes.
6. It may be necessary to field drill the connector plate to
the slide.
7. Connect top plate with (2) 3/8” x 1 1/4” button head
bolts, no washer on top, and 3/8” washer and lock nut
on bottom
8. Position the hand grab bars on either side of the slide so
that the black plug end of each bottom spacer bar held
by a pipe clamp butts up against the slide wall.
9. Make sure the grab bars are vertical, on bubble and no
more than 3 1/2” from the support posts.
SPECIFICATIONS:
Event: Triple Rail Slide shall be constructed of 3/8” double
wall construction has plastisol coated connector plate to deck
with double slide legs and re-bar to ground. Has 2 slide beds
with 4” high sidewalls. Comes with slide guard, post clamps
and hardware.
Hardware: Stainless Steel tamper resistant
MAINTENANCE:
Touch up any marred paint surfaces.
Periodically check hardware for integrity and tightness.
Superficial scarring of the plastic can be ‘healed’ by gentle use
of a heat gun or torch.
Summary of Contents for Bobbie 911-124
Page 1: ...Page 1 800 727 8180 www sportsplayinc com 911 124 Model Bobbie...
Page 3: ...Page 3...
Page 13: ...Page 13 Footing Diagram...
Page 15: ...Page 15 Side view of installed post...
Page 25: ...Page 25...
Page 52: ...Page 52 1 2 4 3...
Page 53: ...Page 53 5 6 8 7...