902-958 DUAL LEG PRESS STATION 

INSTALLATION INSTRUCTION 

FOOTING INFORMATION 

!

 

You must place the bottom of the footing frame on a 
suitable flat blocking material to prevent it from sinking 
further into the soil.  We recommend you use a brick, block 
of wood or gravel.  The footing depth of 2’ includes 6” of 
blocking material (refer to image at right and images on the 
next page as a reference). 

!

 

It is the owner/installers responsibility to check local 
building codes and to comply with those codes.  All footing 
depths listed here are recommendations and local soil types 
and frost lines may require a deeper and/or wider footing 
depth.  If that’s the case you must add more blocking 
material to accommodate the deeper footing, as the footing 
frame will still only be installed at the depth listed in this 
instruction manual. 

!

 

The top of the plate on the top of the footing frame needs to 
be installed flush with the top of the concrete surface.  

 

 

 

Summary of Contents for 902-958

Page 1: ...ight 271 lbs MAINTENANCE As the owner of the equipment you are responsible for maintenance of the equipment and the surrounding area A maintenance schedule must be developed and the equipment inspecte...

Page 2: ...TION PARTS LIST ID DESCRIPTION QTY 1 Dual Leg Press 1 2 Footing Frame 1 3 Mounting Cover 2 pieces 1 4 Hex Nuts 4 3 8 x 2 Button Head Bolt 2 3 8 Flat Washer 2 7 32 Allen 1 NOTE Keep a copy of these ins...

Page 3: ...n the next page as a reference It is the owner installers responsibility to check local building codes and to comply with those codes All footing depths listed here are recommendations and local soil...

Page 4: ...ng OD WARNING THIS EQUIPMENT IS DESIGNED FOR HEALTHY PEOPLE AGE 13 AND UP INSTALLATION TIPS TROUBLE SHOOTING Installation of the equipment is easy since the equipment itself is already assembled Alway...

Page 5: ...op plate is flush with the surface of the concrete After the concrete has cured install the equipment onto the footing frame by sliding the equipment into position and attaching with the nuts provided...

Page 6: ...t all metal components for coating damage If powder coating needs to be repaired sand surface and mask off area Coat with primer and once the primer has dried paint with color matching touch up paint...

Page 7: ...STED INCLUDE DATES AND SIGNATURES Inspection Checklist Recommended Frequency Grade Pass Fail NA Date Inspected Date Repairs Completed Inspect Hardware Weekly Inspect Plastic Components Weekly Inspect...

Reviews: